Pierre
Auger Project
Progress
Report
September,
October & November 2004
Summary (photo album)
We have reached the halfway point in the construction of the fluorescence detector system and are making rapid progress on the last half. We celebrated the inauguration of the Los Morados building at the November collaboration meeting. This event provided many Auger collaborators with perhaps their only opportunity to visit this building in its remote and breath-taking setting. The installation of telescopes at the Los Morados building is ahead of schedule and the commissioning should be complete by the end of March. (See images of the Los Morados shutter installation in photo album). If all goes well we will break ground for the last building at Loma Amarilla at the northern edge of the array in early 2005.
As of 17 December there are 562 surface detector stations (more than one third) taking data. A total of 616 stations are deployed in the field and awaiting water and/or electronics. Our surface array deployment rate is still limited by our ability to deliver water to the tanks in the field. Our goal is a water delivery rate of an average of 72 during the fair weather months. So far we have not approached that rate. This is due in part to an exceptionally rainy spring, the increasing distances that the transport tanks must go to access the tanks and on a number of mechanical failures. A strong effort is being make to speed water delivery.
The last communications tower at Loma Amarilla is complete and antenna rigging is underway.
Although we have received some encouraging news from several countries about new funding to complete the array, short term funding remains a serious problem. As of now we only have sufficient materials and components to complete 1100 stations. This will allow us to continue deployment until about July of 2005.
WBS 1.1 Fluorescence Detector (Jonny
Kleinfeller – Karlesruhe)
Coihueco
Finally the three service cranes have been installed. Operation of the
cranes
requires minor modifications of the air conditioning ducts above the
telescopes.
The missing four corrector ring frames have been assembled and will be
mounted,
as soon as the cranes can be used.
Los
Los Morados
Reference points, aperture boxes, mirror support structures and mirror
mounts
are installed and aligned for 6 telescopes. The shutter frames are
installed,
only the doors, seals and the drives to be done.
The air conditioning system has been delivered and is going to be
installed
this week.
A team from
At the Galpon Rodrigues are 6 cameras fully assembled, ready to go to
Los
Morados in February.
The filters will be assembled between Christmas and New Year.
Installation at Los Morados is slightly ahead of schedule.
The road to Los Morados is deteriorating fast.
The power line is due to be connected next week.
In November
WBS 1.2 FD
digital electronics
and readout systems (Matthias Kleifges - IPE)
Installation
work in Los
·
During
the collaboration meeting the new FLT/SLT firmware (version 8Nov04) and
the SIB
firmware V4.5 were installed on all telescopes in Los Leones and
Coihueco. The
firmware fixes a minor bug in the SLT timing and a difficult to find
bug in the
FireWire hardware interface.
·
The
new firmware of the GPS clock V4.0 makes the handling of triggers from
external
sources more flexible. Now it is possible to disable veto signals from
the
Lidar at times the shutters are closed. This allows intense Lidar
operation at
the beginning of the shift without disturbance to the relative
calibrations
process.
·
Together
with R. Moussa the interface between FD GPS clock and Lidar was
implemented on
Lidar site. During its operation the Lidar requests triggers from the
GPS clock
at well-defined times. Operation in the field of view of the telescopes
(or
close by) now vetoes the SLT/FLT operation via a hardware signal. At
present,
there is only a low repetition 20 Hz laser available in Los Leones,
which will
in the near future operate mainly outside the field of view to avoid
veto dead
times.
Progress
in DAQ and related software: (by H.J.
Mathes and Kopmann, FZ Karlsruhe)
·
During
the reporting period the DAQ was improved to version FD-das-2.7.1-39.
The main
changes streamlined the logging information, improved the error checks
in the
communication with the MirrorPC and Calibration PC and fixed some bugs
in the
Third Level Trigger (TLT).
·
The
latest version also writes now in the run trailer information of the
veto time
counters, the dead time counters and the life time counters, which can
be used
in future for efficiency calculations.
·
Cases,
where parameters from the GPS clock for time corrections, are missing
are now
handled using average parameters and flagged in the data.
·
The
DAQ code contains already sections for the planned (but not yet
enabled)
inter-camera trigger. The inter-camera trigger scheme will handle
situations,
where a long track ends in the outermost column and the adjacent
telescopes are
triggered by a hardware signal. The scheme can not improve the trigger
efficiency,
but avoids loosing the information from 1-3 pixel tracks in the
adjacent
telescope.
·
In
his endeavour to find the bug in the FireWire communication Andreas has
reworked the hardware near library FdHwlib and the feshell program.
Now, e.g.
the re-use of sockets accelerates the restart of some programs and bugs
in the
readout functions for pixel multiplicity are fixed. The same code can
now
compiles at SuSe 7.3 and SuSe 9.x. In addition, feshell and the fdhwlib
support
the new features available with the new GPS clock version V4.0 (see
above).
Progress
in Slow Control hardware and software:
(by
· New light sensors with higher sensitivity and offset adjustment will replace the current type in all buildings.
·
The
SCS equipment for Los Morados is shipped for installation in January
2005. The
SC terminals are pre-wired in
·
Frequent
operation de-adjusts the FS curtain due to mechanical weakness. Until
the mechanics
is fixed the SCS software will keep the curtain lifted even in standby
mode
during the shift period.
·
Software
is installed on all SCS computers to forward event log-files and
warning
messages via emails to
·
The
SCS now allows a more detailed display of the HV system status. If the
connection to the HV-system is lost, the shifter can cycle the HV-crate
power
or try to reset the crate.
·
Ideas
to further improve the system stability are in progress. It is planned
to
rewrite the software such that only a single task accesses the disk to
write
log messages. An acoustic alarm in CDAS should notify the shifters of
automatic
changes in the buildings.
WBS 2.1
SD Site (Ingo Allekote – Instituto Balseiro)
As of December 8th,
2004, 616
assembled Surface Detectors are deployed in the field. Of these, 592
are filled
with water and 561 of them have electronics installed. Another 57
detectors are
in the AB yard ready for deployment. 153 more tanks are available,
sitting in
the AB yard and waiting to be assembled.
A new SD baseline layout has been agreed on.
With this
new layout, positions of SD detectors cover all the area in the North
up to
Loma Amarilla. Some 70 "spare" positions have been included.
Aldural (now called "Hydro") provided the 3000
kg of square tubing for brackets, which were used to assemble 250 new
brackets
at Aberlum. These have already been delivered to Malargue. 360 more
brackets
have been ordered from a new provider, Equipos y Proyectos.
In October-November 2004, 207 liners were
produced. On
November 30, 2004, the liner factory at UTN in
On October 29, 2004, the Liner Production Plant
was
certified without Non Conformities nor Observations according to ISO
9001:2000
IRAM-IQNet !!!
The fourth water transport tank, Tk-12-DELTA,
is under
construction at Asorey. It is expected to be finished before the end of
the
year. All the accessories for this tank (hoses, filters, pumps, etc.)
have been
ordered.
Two fiberglass tanks were manufactured by
Petroplast
and delivered to Malargue. They will be tested in the near future.
More contracts for land access and permission
for SD
deployment have been signed. In particular, the contract with Valles
Mendocinos, who owns the area south of Coihueco, has been signed.
WBS 2.2. Surface Detector Electronics (Tiina
Suomijarvi – IPN Orsay)
The electronics deployment is progressing
smoothly. Currently about 550 tanks are
running
on the
We have
currently received about 50% of the PMTs from Photonis. The delivery
rate is
still kept at 144 PMTs per month. The most failures in the PMT testing
(PMT
test facility in Malargue) were due to over linearity. This has now
been
corrected by introducing a new design yielding better linearity. The
new design
has been validated by the tests in

Figure 1. Statistics concerning PMT tests in
Malargue (from F. Suarez)

Concerning the PMT (PMT+base+cables)
field failures, as reported by
|
Unstable, temperature related problems |
37 |
|
Poor d/a ratio |
5 |
|
High power consumption |
7 |
|
No calibration |
22 |
|
Gain fluctuation |
4 |
|
Unstable in time |
2 |
|
Total |
77 |
Table
1. PMT field
failures (from
Some
of the
problems were analyzed as being due to the following failures (from
|
Unwelded FL |
1 |
Poor d/a ratio |
1 |
|
Broken glass (2 old bulb designs) |
4 |
No calibration High consumption |
2 2 |
|
PMT mechanically unstable |
1 |
Unstable, temperature related |
1 |
|
Base failure |
2 |
Short circuit No calibration |
1 1 |
|
Bad connector |
16 |
Unstable Temperature related, no calibration |
3 13 |
|
Total |
24 |
|
|
Table
2.
Analysis of the PMT field failures (from
Total
53
field failures were not yet understood, the major part of them (33)
being
related to unstable behavior as a function of temperature. During the
Malargue
meeting, it was decided to remove all the PMTs presenting failures from
the
field (they were left on the field for further monitoring). Some of
them will
be sent to
Concerning the electronics kits, the failure rate in the SDE Fabrica tests is small, below 1%. The FE field failure rate is small, about 1%. The UB field failure rate is about 6%. The most failures concern the UB fuses (49%) or the software upgrade (30%). The UB fuse problem has been analyzed by the CdF team after the Malargue meeting. About half of the failures occur multiple times on the same tank which seems to indicate that the failure might be due to the regulators. Further analysis is currently in progress. As a possible corrective action fuses can be changed into bigger ones on the UB board in Malargue.

Figure 2. UB field failures (from M.
Videla).
The performance of the array is
monitored. Table below shows the number of PMTs failing the performance
specifications.
During the period September-October
the percentage of PMTs out of specification was below one percent
(except the
VEM area).

Table 3. PMT
performance monitoring (from D. Barnhill
et al.)
The figure below shows the
Time-over-Threshold trigger rates. The trigger rate in recently
deployed tanks
seems to be higher that “old” tanks. It reflects the larger VEM
area/peak values
in new tanks (see figures below). This can be due to a stabilisation
effect and
needs to be carefully monitored.

Figure 3. Time-over-threshold
trigger rates. The rate is clearly higher in recently deployed tanks
(from P.
Ghia).

Figure 4. Time-over-threshold rate
as a function of the VEM area/peak (from P. Ghia).
The commissioning and performance
studies of the surface array are still in progress.
WBS 5.0
DPA/Offline-
(Stefano Argiro – INFN)
The Offline project proceeds at full throttle. Version 1.0.0 has been tagged in the CVS repository. The group is refining the installation procedure, then a public release will be prepared.
This version provides baseline chains for Fd/Sd simulation and reconstruction, plus hybrid reconstruction. We'd like to stress that the code does not yet represent the best
knowledge of the collaboration in the various fields of investigation. It provides some working yet basic algorithms, that we hope will serve as foundation to build the most effective simulation and reconstruction package.
The Offline project has undergone a Review, in which many achievements have been recognized.
The review panel expressed some concerns that will be addressed, but overall the project was rated very high.
Last, but not least, following the positive
experience with
the first "DPA - Offline school" in Torino, another school will be
held in
WBS 8.0 Education and
Outreach (Greg Snow –
The Auger Observatory was featured at CERN’s 50th
Anniversary Open Day held on October 16. The photo gallery of this
report shows
the Auger display that included tabletop sized SD and FD models,
posters, two
laptops showing Auger images, Argentine flags,
An Auger Observatory poster is also featured in a permanent exhibit entitled “From Quarks to the Cosmos” that was mounted on the 15th floor of Fermilab’s Wilson Hall in October.
The
On November 8 and 9, Rebeca López offered a hands-on physics teaching methods workshop to about 20 Malargüe teachers for grades 1 to 7. Using readily available materials, the teachers developed a number of simple experiments to illustrate a wide range of physics principles in response to questions posed by Rebeca. After the workshop, Rebeca documented the experiments in a detailed users manual so that the teachers can reproduce the experiments they developed in the classroom. The workshop was lively and interactive and was deemed by the participants to be very successful. The photo gallery of this report contains images from the workshop.
The Los Morados FD building was inaugurated in a
ceremony on
Saturday, November 13, attended by many collaboration members and
visiting
dignitaries including the governor of
During the collaboration meeting, first
organizational steps
were made for an Auger-sponsored science fair foreseen to take place
during the
November 2005 collaboration meeting in the
The Auger collaboration participated in the Malargüe Day Parade on Tuesday, November 16, for the third time. About 80 collaborators marched behind a large banner, and for the first time two Auger vehicles brought up the rear of the procession. Photos from the parade appear in the photo gallery of this report. The collaboration picnic took place the same afternoon at the Castillos de Pincheira. The collaboration was treated to traditional music from local musicians and to a tango demonstration by local dancers.
Randy Landsberg,
Director of
Outreach for the Kavli Institute for
Cosmological
Physics at the
Beatriz García
reported on several ongoing activities in
On September 1, Greg Snow and John Harton
traveled to
WBS 9.0 Observatory Operations – (Julio Martino
Rodriguez
- INFN)
The work of the operators during the FD shifts is
slowly
becoming a routine. The communication between the operators and the
experts in
each part of the data taking system is helping to quickly solve
problems. A
special e-mail account is used to exchange information and requests of
debugging tests from the experts.
The data taking time is optimized by using a program that calculates
the
position of the moon and allows to close
each
individual shutter whenever the moon is closer than 5 deg. to the field
of view
of the telescope. Many thanks to M. Prouza
for
developing this software.
The FD data stream was split into two streams at the beginning of
October. The
files mirrored in
of the background measurements for October. This was solved and now the
data
flow and mirroring is back to normal. The problem was only related to
the
background files (known as bgrecord
files), the rest
of the files were transferred and mirrored correctly.
Different measures were agreed with the responsibles
of the atmospheric monitoring devices to minimize the interference with
the FD
data taking. We are getting to the point were the data is completely
clean and
all the events triggered by external devices are sent to special files.
People
doing tests with the atmospheric devices are requested to agree in
advance the
time slot for these tests with the FD-SOC. This will prevent
interference with
the data taking.