Pierre Auger Project

Progress Report

 

Summary (photo album)

 

Tanks are once again arriving at the Observatory from Brazil.  We are beginning to close in on the deployment and commissioning of detector station number 1600.  The staff is easily able assemble and deploy detector stations at the rate that the tanks are received – about 18 every two weeks.  There are now more than 1570 tanks in the field of which 1533 are filled with water.  The latest news is that all tanks have now been deployed on the land of the “Italians” and filled with water.  Many of the tanks not yet filled with water are in places that currently cannot be accessed by water delivery equipment.  Although we can now enter the area that corresponds to the hole with 54 locations, final negotiations have not yet taken place with the land owner.

 

That strategy for completing the base line array is to deploy and commission 1600+ tanks in available positions.  When the remaining positions become available by agreement with the land owner or become dry enough for access, the staff will continue the deployment up to about 1650 stations.  After that tanks will be moved as necessary to fill and smooth the array.

 

The cause of the instability in some of the PMTs has been isolated as a grounding problem in the base.  A fairly straight forward procedure has been developed to make the necessary repair in the field. 

 

The HEAT project to install three high elevation fluorescence telescopes is moving ahead.  Permission to rent the land near the Coihueco fluorescence building has been obtained and construction has begun.

 

Good data is being taken by the groups developing radio detection of showers.  For the first time the LAL, LPSC and SUBATECH group has recorded self-triggered shower events that are in coincidence with the main array events.

 

The American Institute of Physics has included the Auger correlation result in the list of the ten biggest physics stories in 2007.

 

WBS 1.1.3 Fluorescence Detector Calibration (Jeff Brack - Colorado State

University)
 
With approval of FD task leaders, the calibration group has agreed to form two subgroups, focussing on the absolute drum calibration and on the relative calibration analysis.  Rossella Caruso will lead the relative calibration group.  The overall organization will remain as a single
calibration group, due to the close relation between the two efforts; the intent is to allow the drum group to return to it's primary task.
 
Two more data disks have been loaded with relative calibration data in Malargue. This nearly completes the copy of ~1 Tb of data from the Malargue server to other sites (Lyon and Catania).
 
Work continues on establishing new calibration epochs to include the recent Loma Amarilla calibration.  A parallel effort will establish 5 earlier epochs, extending the usable data for analysis back to January 2004.  Work also continues on establishing the nightly calibration
database.
 
Calibration labs in Malargue and Colorado are both moving.  The Colorado lab move from CU to CSU is nearly complete.  Plans are underway for moving  the Malargue lab from the galpon to the AB.  Several options for defining dark room space in the AB hall are being considered.

 

WBS 1.1.3.3 Fluorescence Detector Atmospheric Monitoring (Stefan Westerhoff – Wisconsin)

 

Lidar (reported by Jorge Rodriguez)

 

The lightning protection system for Loma Amarilla is now in place.  Because of the volcanic ground, the construction was particularly difficult at this site.

 

Raman lidar status (reported by Vincenzo Rizi)

The system was operating in its standard configuration since November 2005, although an intervention to obtain better mechanical stability was done in August 2006, and a change in the DAQ electronics in April 2007.
In July 2007, probably due to the extremely low temperatures attained in Malargue, the laser broke and is now in its way to the manufacturer for reparation.

Anyway, since August 2006 the system is in a (relatively) stable configuration. It is therefore possible to compare the Raman data with CLF measurements until January 2007 (official CLF reconstruction) or to Napoli group CLF reconstruction (until May 2007).
It appears that there is both a large dispersion of the data, and a relative shift of the values. In particular Raman Vertical Aerosol Optical Depth (VAOD) values tend to be larger than CLF ones. On the other end, if we normalize the VAOD measurements in each month to a different reference (clear or Rayleigh) night, a better agreement is obtained.
The aerosol backscatter measurements of the Raman lidar are less affected by optical or mechanical instabilities of the system setup, and good aerosol density profiles can be obtained, which, in most cases, clearly show the behaviour of the aerosol into the planetary boundary layer. The values of the integrated backscatter profiles are proportional to VAOD in the case of single aerosol composition, and other strategies to compare with CLF data are possible (to obtain VAOD values from integrated backscatter ratios would require knowledge of the Lidar Ratio).

As said before at present the laser head is broken and awaiting repair. In the meantime there are projects to improve the stability of the system and the signal/background ratio. As for the stability, some improvement will follow from the planned change in cover movement and of the lidar roof in LL.
Concerning the signal/noise ratio we need to optimize the optical coupling between the telescope and the optical fiber (to the receiver box). This optimization will be tested in laboratory in L' Aquila and duplicated in LL. Also work on the DAQ electronics is needed, and this work can be done in L'Aquila too where a (partially) duplicated system exists. A possibly very useful change might be the substitution of the Oxygen raman lidar channel with a Water Vapour one. This only amounts to change some filters in the receiver. Presently the Oxygen channel is of little use, while the Water Vapour channel can give twice a day an estimate of humidity up
to 5-7 km which is relevant for the fluorescence yield.
Finally, it is important to notice that the Raman Lidar can easily take measurements in periods outside the FD shifts. These measurements are of little relevance for Auger, but may be of interest for the larger atmospheric community. We are presently starting collaboration with the Rosario group, both on the analysis of the data for Auger and their possible wider atmospheric physics interest. In this context a possible contribution from atmospheric physics groups might be looked for.

WBS 1.2 Fluorescence Detector Electronics digital electronics and readout systems (Matthias Kleifges – FZK-IPE)

 

DAQ software (H.J. Mathes)

 

The main developer of FD-DAQ software – H.J. Mathes – is for about 2 month in Malargüe to work on following problems:   

·        The most severe problem in the past was a crash of the Event builder part, which stopped data taking, especially, if the inter-camera trigger was enabled. With the help of various tools (valgrind, efence, gdb) several memory leaks were found and removed. In addition, the data structure of the EvB was changed as ROOT containers were replaced by STL containers. Now the software runs much more stable.

·        The latest DAQ version 3.3.-2 for the December shift fixed the bugs #715 (critical disk space), #714, # 547, # 697 and partly bug # 709 (not completely). It also implements the new TLT developed by A. Schmidt, which is active since the September shift.

·        A rudimental inter-camera trigger was implemented in the DAQ, but tests showed that the extra events would flood the FD-DAQ in case of lightning. We are working on a more intelligent solution, which would leave the data of the neighbour telescope for a longer time in the crate and initiate a readout only, if the triggering event was accepted in higher levels. This scheme will be implemented in FPGA firmware of the SLT.

·        It is cumbersome to operate 4 FD eyes one-after-the-other and start each DAQ separately. Thus, a Run Control GUI to steer all FD sites at the same time is needed. Within the frame of AUGER ACCESS several options for the protocol to steer the communication were investigated. It is intended to provided a GUI with reduced functionality (compared to the current options), but still sufficient for normal FD operation.

 

Hardware work / changes in Malargüe

 

·        The high amount of data for the monitoring and calibration filled the hard disks in the FD buildings to fast, especially, if the replication to the server at CDAS failed for any reason. N. Kunka installed during his stay 142 GByte raid data disks which provide a 3.5-times higher capacity.

·        Sascha Menshikov repaired defective (or suspicious) front-end boards of the FD electronics. By adding an additional blocking capacitor on all SLTs the sensitivity of the internal PLL to spikes was reduced. This solved the “missing seconds problem” of one SLT module.

·        A problem with the LCU leading to multiple ping responses in the LAN was localised, but needs further investigation in Karlsruhe.

 

R&D for Auger North and the HEAT proposal

 

·        We have completed the production of a first versions of the HEAT modules:
- The new SLT is completely tested, i.e. the interfaces between the FPGA and all periphery (memories, backplane buses, PCI, PrPMC module) are working. Basis read/write operations into the FPGA internal memory from the processor module are possible with 40 MHz. Minor changes are incorporated into the circuit diagram. The PCB design for the modified version is currently done.
- With the new SLT and FLT we have started intensive tests of the high-speed backplane. With our prototypes we could drive the pixel bus as well as the address bus with 40 MHZ. The abandonment of a +5V supply allows us to add 6 more bus lines, which increases the flexibility of data exchange. These modifications are incorporated into a revised circuit diagram. The PCB design will start after the SLT design is finished.
- The FLT prototype was tested together with the new analog board design. We found no errors in the design, tried successful the gain adjustment and measured the noise performance and filter characteristic. Also the full data chain on the FLT from FPGA to ADC and memory (QDR ram and SDRAM) was successfully working with 40 MHz. The next PCB design for the FLT will start in January 2008.

·        In total 5 crates are now procured from Wiener of the new type. Of those, 3 are wired with the prototype backplane, the remaining 2 have to be equipped with backplanes of the modified type.

 

WBS 2.1 SD (Ingo Allekote – CNEA)

 

By the beginning of November, the tank delivery to Malargue resumed after a long stop due to financial problems with the trucking company in Brazil. Three tank shipments, with 18 tanks per shipment, were received from November to mid-December, totaling 54 new tanks in Malargue. More tanks are expected to arrive to Malargue in January.

In the period October-November 2007, 15 surface detectors were assembled, 32 deployed in the field and 40 filled with pure water. 31 e-kits were installed. As of November 30, 2007, there were 1559 SDs in the field, of which 1515 were filled with water.

Batteries still pose a problem, as a huge fraction does not pass the quality control.

Two insulated tanks, originally designed for thermal test studies, were assembled. Due to their different inside shape, texture and thickness, some changes in the assembly procedure were required. New procedures for assembling insulated tanks are being developed.


There has been some progress with landowner issues. The Province of Mendoza has passed a decree allowing Auger the right of transit in the land owned by Felix, which is being rented by Sat. In a next step we plan to negotiate directly with Sat, but negotiations should be more favorable based on the existence of this decree.

Contact has also been made with the landowners of the fields south of the Italians (Arias-Arenas). Although a portion of this field is in dispute between Arias and the Italians, they are willing to grant us access if Auger repairs some access roads and some bridges. Work is under way.

Negotiations have been carried on with Pietrelli, who owns the land to be occupied by Amiga. We plan to lease this land with an unrestricted access permit, to use it as a test ground for various experiments and prototypes. We expect to reach an agreement with Pietrelli very soon.

 

WBS 2.2 Surface Detector Electronics (Tiina Suomijarvi – IPN Orsay)

 

Status on the “raining” PMTs

 

The following table shows the current statistics (October 31) concerning unstable PMTs (so called “raining” PMTs).

 

1429 running stations

414 “unstable” stations

261 stations: 1 raining PMT

121 stations: 2 raining PMTs

32 stations: 3 raining PMTs

599/4287 raining PMTs (≈14%)

 

The potting procedure was revised and the quality increased early this year. There are currently about 170 stations on the field with new potting. It seems that the PMTs with new potting have less instability problems (about 5%). However, this result still needs to be confirmed.

 

There is a clear winter-summer effect. During cold weather, the problem decreases, as can be seen in the fig. 1.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Figure 1. Number of unstable tanks as a function of date. A drastic decrease is seen around June-July-August.

 

Measurements were performed by the test tank Jamie (AB). This tank had at one period a “raining” PMT. Interesting conclusions were drawn from these measurements. During the “raining” period, a significant fraction of the total charge is apparently charging an extra parasitic capacitance, which adds a characteristic time of hundreds of nanoseconds to the dynode chain. This has as effect to decrease the peak value and enlarge the signal (see fig. 2) yielding to an increase of the ToT trigger rate.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Figure 2. Average pulse shape. PMT’s with “raining” behavior have wider pulses.

 

The average pulse shape is available in the online calibration and it could be possible to implement an off-line T1 by using de-convolution. This would also allow to have a uniform detector trigger efficiency (independent of water quality).

 

Careful tests of the “raining” PMTs have been performed in Grenoble. A test bench including temperature cycling and humidity monitoring was developed. A temperature cycle similar to the field conditions was used (5°-35°-5° in 24h). The “raining” effect was reproduced and it was shown to be located on the base. It was also confirmed that the pulse shape in “raining” PMTs was enlarged. By proceeding component by component, the problem was identified to be located on the grounding of the dynode cable. When extra grounding was added the effect disappeared. These tests were reproduced for several PMTs (6) with similar results.

 

Currently extra grounding is added for all the PMTs deployed to the field. For those who have already been potted, it is possible to add a grounding cable by slightly removing the potting, as shown in fig. 3.

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure 3. Extra grounding is being added to the dynode cable connection on the base.

 

 

Several actions have been taken to understand and to reduce the “raining” PMT effect:

Increase the quality of potting

Insulate against high temperature

Studies in laboratories and on site

Tracing back components

 

 

Furthermore, it has been checked that this effect does not affect analysis (above the acceptance saturation). 

 

It seems now that the problem is located and a plan for software and hardware repairing is being implemented.

 

WBS 3.0 Comms (Jorge Abraham – UTN)

 

My information to November 30Th:

- AntennaKits mounted: 1509.

- AntennaKits made:    1660. We finish this part of Task !!!!!

- I make a control periodic of the SD Signal quality.(See Image: RadioSignal.JPG).
About bad links, We will change some AntennaKits for High-Gain Antenna Kit to solve the problems. May be during the first six month from 2008.

 

WBS 4.0 Online Monitoring (Cyril Lachaud – APC)

 

Concerning the Auger Monitoring Task:

 

A new web release has been installed on both moni in Malargue and apcpaox in Paris.

We have some problems with the configuration of moni in Malargue. There are some IO problems that need to be solved.

The second moni computer will be used to determine the best parameters before replacing the actual one (that will then be used for the nagios system to monitor all the hardware/software of the Observatory inside the CDAS network).

 

WBS 5.0 DPA/Offline- (Bruce Dawson, Markus Roth and Tom Paul)

 

A tag for hybrid simulation production has been applied, and tests for simulation production have got underway.
 
Most of the SdCalibrator work required to reflect CDAS v4r6 Ec has been completed.  An SdCalibPlotter module has been added which provides visualization tools for the various algorithms employed by the new SdCalibrator.
 
The ParticleInjector module has been substantially revised.
 
Simulated tank calibration constants are now retrieved from the detector description, rather than from a configuration file in the SdSimulationCalibrationFiller module.  If you change tank
simulations, the appropriate calibration constants are read from the detector automatically, using the simulator name as a key. Note that the standard simulation module sequences have been
updated accordingly (now the calibration filling happens after the tank sim).
 
Evaluation of options for a more modern and maintainable build system are underway.

 

WBS 9.0 Observatory Operations – (Julio Rodriquez Martino - INFN)

 

FD Operations

Operation of all telescopes in all buildings was normal, with only minor and known problems.
The variance limit, that allows to automatically close the shutters, has been fine-tuned and has worked properly. Several new pages have been added to the FD monitoring system and it's now a very useful tool for the shifters.

- The bug in the FD elog was solved, now the shifters are able the log information directly to the database and also to recover from the crash of the browser as the elog itself is periodically saved. There's also the possibility of searching in previous entries to see how problems were solved.
- During the December shift, the satellite providing weather imagery for the site (GOES-12) was taken out of line due to maintenance activities. Even not having a direct impact on the operation, these satellite images are useful for the shifters to 'forecast' the future data taking conditions for the next couple of hours. It is also possible to identify lightning storms around the site that
could cause interference in the DAQ which are quite common during summer time.
- The variance limit watchdog has been fine-tuned to prevent unexpected closing of the shutters.
- A summary page has been added to the FD monitoring website. It includes a summary of the background loop data, the trigger rates, the latest APF&CLF shots and the status of the weather from the Slow Control, all the displays have associated timestamps and are color-coded to easily detect which variable has gone out of range or if some information is out of date. Besides this, some debugging of other php scripts was also performed.
- Several scripts that perform checks before the start of the run were troubleshooted.

This year's operation was generally normal. The largest problems were due to an extremely hard winter with several snow storms which prevented normal data taking.

 

WBS 9.0 Observatory Operations cont.  – (Ricardo Sato – Southern Observatory)

 

During October, 2007 the SD operation was quite fine. On the other hand during November, 2007 and beginning of December had some changes and one strange instability of the array. Following we have a small descriptions of the what happened.

During the same period of the Collaboration Meeting (2007/Nov/12 ~ 2007/Nov/17), the instability (all array stop to send data) was related with a test to send a new Unifier Board software. The previous software version could not handle properly a problem which looks to be
related with the GPS signal and make stations lost synchronization. The new software version is supposed to handle properly this problem, although it is still temporary version.

During 2007/Nov/24 and 2007/Nov/25, there was a general power cut in Malargue and almost all equipments of CDAS have been turned off, except those which are really essential to the operation of the array. Unfortunately this effort looks to be almost lost. Although CDAS looks working fine, the event data was not recorded because a apparent problem related with the main disk used to store all event data (for some reason it have been remounted as "read only" and it was not possible to write the event information in it). This problem has been fixed only on 2007/Nov/26. People which use the T2 information or log files should take care with this particular period, since the problem do not affect those files.

On 2007/Nov/27 part of one equipment at the communication Malargue tower stop to work and the link of SD channel between Los Leone’s tower and Malargue tower have lost. In the same day (afternoon) the Los Morados tower stops to work. It looks to be a power protection which
cut the power in Los Morados. A day after the problem has been fixed and the batteries used to the communication have been replaced in Los Morados.

On 2007/Dec/02 we lost connection with Los Morados again. The problem looks to be generated by the power protection in Los Morados tower which turned off. It looks to be generated by a problem in the general power line in Los Leones and Los Morados buildings. The voltage in
both buildings was too high and it looks damage also one UPS in Los Leones (Fluorescence Detector).

At the same time which the problem in Los Moarados has been repaired (2007/Dec/03), one radio equipment has been replaced because it looks to have problem with synchronization.

On 2007/Dec/06 the total number of stations working at the same time (looking T2 information) was much bellow the normal and all the array looks unstable. The situation became worse with time and the number of working stations on 2007/Dec/08 the total stations working as very
close to 0. The strange thing was almost all station was answering to CDAS requests and it could send data event data; however the trigger information (T2) was not recognized by CDAS. Looking to the communication system, everything looks fine but because of the replacement of equipment in Los Morados few days before, it looks to be something related with communication. During this period, many actions have been made (reset communication system, restart the all CDAS process, and so on). The system have recovered only turning off all CDAS machine and turning on again.

 

 

Radio Detection R&D – (Ad Van de Berg – KVI)

 

Continued data-taking is taking place near the BLS and the CLF. The uptime near the BLS is hampered by power failures and occasional required hardware resets, but valuable data are still recorded (KVI, Nijmegen, NIKHEF). For the first time, self-triggered coincidences between baseline detectors and radio antennas have been recorded for the stations near the CLF (LAL, LPSC, SUBATECH). It shows that at both locations in the array results are being recorded and that substantial progress is being made in this R&D project.

Results from simulations by FZK, KVI, and SUBATECH on the shower development and subsequent radio emission are being studied in more detail, leading to new insights. These results are being incorporated by RWTH into an end-to-end simulation for shower-induced radio signals. Work has started for the development of the radio-offline software by the University of Wuppertal.

Near the BLS a new array of antennas and new electronics will be deployed in early 2008. For this purpose NIKHEF has produced new 4-channel 200 MHz sampling scopes. KVI has designed and constructed a local station providing wireless connectivity to the BLS and local power from solar panels. The group from RWTH has made a new design for a log-periodic dipole antenna, which will be more stable against heavy wind loads. These antennas will also be used for additional testing at various sites in Europe. The FZK has produced more low-noise amplifiers for the front end. At a distance of about 700 m from the BLS the first 4 new poles have been mounted under supervision of the staff of the Observatory. These local stations can be used to test various trigger schemes which are presently under development at FZK, Nijmegen, and KVI.

Funding has been received for the purchase and installation of GHz receivers near Coiheco for the initial studies of the molecular Bremsstrahlung R&D project (OSU). Meanwhile work is progressing at FZK, LAL, LPSC, NIKHEF, and SUBATECH to optimize various components of the station hardware and embedded software.

 

HEAT enhancement -Hans Klages (FZK)

 

Preparations for the HEAT hardware installations are moving forward steadily and with good speed. The second 40` container with all the parts for the tilting base plates, hydraulic etc. arrived in Malargue on November 7. All material is now stored at the Central Campus. 
On the same day the third container with the steel frames and insulation material for the HEAT enclosures left Karlsruhe. This one is supposed to arrive in Malargue at the middle of December. All the heavy stuff will be on site by then.
 
Norberto Fazzini and Alan Watson went to meet the Argentinean representative of the HEAT landowner to discuss the land lease contract. Although they in fact did not meet him, land access was granted for the building company even prior to the final signatures. It means that the site preparation might really start next week, even before December 1, thanks to all this effort.
This is a big step forward for the HEAT subtask. We hope that our own hardware installations will commence early in March. 

 

AMIGA - Alberto Etchegoyen

 

AMIGA has now three interconnected tanks with WiFi (Jamie, Larabelle, and Didi) in acquisition mode and sending the events to Didi, which registers the coincidence events. In the near future the system will be used in the field. In short SBC appears to be trustworthy for AMIGA.  The FPGA AMIGA programming is nearly finished and its front-end PCBs are shortly to be sent to manufactures.