Pierre
Auger Project
Progress
Report
Summary (photo album)
As a result of an intense effort in the past three months, significant improvements were made in the data taking operation in the Fluorescence Detector, CDAS and Comms. In particular, a tentative solution to the previously intractable Fire Wire bug in the FD readout has been found. Although much work remains, we should see much improved efficiency in the data taking.
There are now 1067 tanks deployed in the field of
which 914
are taking data. Deployment has slowed
substantially because of the lack of new positions.
Large areas in the north remain inaccessible.
The
Work on the Loma Amarilla fluorescence building has started but seems to be progressing slowly.
The Auger Celebration was a great success. Twice as many people attended than had been expected. Many important visitors told us how impressed they were with the Observatory.
WBS 1.1 Fluorescence Detector (Jonny
Kleinfeller – Karlesruhe)
FireWire
Bug:
We have at least a temporary solution for the FireWire bug. In fact there are two solutions. One has already been
tested, the other
is going to be tested this week.
There is obviously a conflict between LAN, FireWire and processor
board. It
turned out, using the LAN port on the processor board, eliminates
the bug,
but has some drawbacks.
The on board LAN is a priory not configured to work with
network boot,
which is required for our system. This can be changed with some program on a flash card, changes in the
BIOS, and
modification of the kernel. It is not an elegant solution, but it
works
and should be regarded as a temporary solution.
The other solution is based on a replacement of the existing LAN card, this has been tested in
I would not be totally happy with this solution, because we still don't
know
exactly why this bus conflict exists, there remains a
risk, that in future with a kernel or hardware upgrade the bug
pops up again.
Status of FD:
There are still three corrector lenses
not yet
mounted, they are on site, but there is lack of manpower.
There is no progress at Loma Amarilla.
The lightning protections of the power lines are still missing, the surge protectors at the three building are
being
installed.
The 3 months stay of Hermann-Josef Mathes
in Malargüe
was very successful. The DAQ software
is much
more stable now, many bugs have been
eliminated.
An upgrade of the Slow Control software is as of today in
operation. A
new interface has been developed to free Slow Control access from MS-Internet Explorer, it has been tested
extensively,
works well, and will, after some extensions and upgrades, become
the
standard access to the Slow Control PC. Currently it should be
used in
parallel to the Explorer access for reliability tests.
We are one step closer to merging DAQ and SCS to achieve automation.
WBS 1.1.3.3 Flurescence
Detector Atmospheric Monitoring (Stefan Westerhoff
–
LIDARs (reported by
R. Mussa)
(1) Lidar Morados commissioning:
The
system is ready to start operations: the high-repetition laser, Licel
and 2 photomultipliers have been installed and tested, and first
signals were
seen (see photos). All subsystems are
connected to UPS, and new cover motors allow to shutdown everything and
close
the cover in case of power outage. Insulation transformers were
installed to
protect the equipment from
faults in the electric power supply. A missing fiber link inside the FD prevented
us from receiving triggers from the FD building. It
should be ready for remote operations by
next shift.
(2) Lidar Coihueco:
Running smoothly. It was possible to operate it
via VNC from Morados.
(3)
Shoot-the-Shower and Runcontrol Software:
GUIs were largely
improved to stabilize running operations.
The communication software between lidar
PCs
and irene was
improved to
remove destructive interferences between sockets which were causing T3
losses. FDmon and SDmon
are now running smoothly.
FRAM (reported by
M. Prouza)
During
the October/November stay the telescope was significantly upgraded and
the most
serious problems, which were limiting its observation capabilities,
were
removed.
First,
the flip mirror (switching the light between the NF camera and
photometer) was
replaced by a semitransparent mirror and second, the not enough sturdy
WF
camera mount was replaced by a new one. Furthermore, the emergency
roof-closure
system using auto batteries was installed.
The
change of the mirror proved to be highly useful, because now we are
able to do
simultaneous observations using both instruments. Most
important is the fact that now we can do
'NF camera guiding' - it is to center the studied star into the center
of the
field of view of the photometer and control this position during the
whole
photometric observation. The only remaining problem is the not optimal transmissivity of the current semi-transparent
mirror,
which strongly suppresses some parts of the light in the spectral range
between
300-400 nm. Therefore, we plan to replace only the mirror itself during
February/March for a more suitable one.
The
change of the WF camera mount revealed that unfortunately not all the
misalignment was caused by the non-sufficient rigidity of this mount.
The
effect was diminished only by a some fraction,
the
remaining part is very probably due to deformation of the support
structure of
the secondary mirror of the main telescope.
However,
we modified our software and we are modeling this WF/NF misalignment
and we
center to different positions at the WF camera for the different
positions at
the sky. For the correction of position
of the star on the NF camera we then use again the NF camera guiding.
Thus,
both changes allow almost regular and successful photometric
observations of
the HAM source since late October and we finally have successful and
automatic
photometric observations of standard stars since the end of November.
The star
observation is still being tuned-up, we are
optimizing guiding scripts and solving some minor
hardware problems with centering movements of the mounts.
To
summarize, during the last months FRAM finally made the transition from
the
testing period to the observation period. FRAM is now regular taking
photometric data of the HAM source and we already have individual
photometric
observations of standard stars. The data processing is also in progress.
The
figure shows the FRAM telescope in its new configuration.
The new mount of the WF camera and the black
box with the semitransparent mirror are visible.
WBS 2.1
SD (Ingo Allekote
–
Instituto Balseiro)
During this period, 120 tanks arrived to Malargue,
from Rotoplastyc (
As of December 16, 2005, there are 1067 tanks deployed, 1042 with water
and 919
with electronics. A total of 433 tanks were installed in the field
during all
of 2005.
The most pressing problem at present is the lack of positions to deploy
new
detectors, as 5 landowners possessing huge fields are not willing to
sign the
access contract. The
Moura
WBS 5.0 DPA/Offline- (Bruce
Dawson, Markus
Roth and Tom Paul)
The Offline team is focusing on preparing the
offline
software for a production release targeted for January. This work
includes
improvements in and debugging of the core framework code as well as
validation
of the OG physics modules, which will be mainly used in the first
production
runs. Previous work on large-scale production, particularly at
UCLA and
the University of Chicago, have helped to uncover several issues that
need to
be addressed in order to run more smoothly in the future.
A developer meeting was held at the CBPF in October to work on
technical issues
and to plan and prioritize future activities. A synopsis of the work
accomplished
and the outcome of meeting discussions is available at: https://www.auger.unam.mx/AugerWiki/RioMeeting2005.
During this meeting, version 1.3 of the software was released, which
includes
new code for reading CONEX files as well as improvements in the
atmosphere
interfaces.
Since the October meeting, some additional tasks have been completed,
while new
projects have just gotten underway.
On the detector description side, we have implemented high level
interfaces to
information in the aerosol and the overall atmospheric quality
databases.
New interfaces to retrieve station positions from the PMS have also
been
completed. Additionally, code for retrieving T2 status from ASCII files
is now
available, and a MySQL-based T2 database
is in
preparation. Work is currently underway to improve database access
speed and
reduce the associated network traffic. The offline framework and
offline
database tools have been installed on the calibration computer in Malargue to support filling the calibration and
monitoring
databases.
The framework configuration machinery has been improved in preparation
for the
production release. Run configurations are now logged and stored
together
with events in the offline
ROOT files. A configuration override mechanism is also nearing
completion, which will simplify the job of generating configuration
files for
production runs. New CDAS/Offline event converters have been prepared
which
allow passing information between offline and the Ec,
Es,
and Er functions of the CDAS code.
This will
support use of these CDAS algorithms from within the offline software.
More advanced designs for underlying foundation code are also in
development
which will greatly reduce the amount of redundant code and ease future
maintenance. These include new intelligent pointer machinery and
a
redesign of some other foundation class.
Exploratory work has also been done in other areas, including
interesting new
techniques for global fitting.
One challenge facing the offline group is the difficulty of dealing
with the
many different combinations of platforms and external package versions
used by
the collaboration.
To this end, we are setting up a BuildBot
system
which will carry out automatic CVS checkouts, builds and tests
regularly on
multiple platforms. This will also help maintain stability
of the CVS head.
The SD reconstruction chain is undergoing a validation phase. In close
collaboration with the UCLA group we are investigating possible weak
points and
failures of the reconstruction.
The so far unsatisfactory reconstruction of some 3-fold events is
tremendously
improved and gives reliable results for the whole data set available.
The
validation is a prelude for the forthcoming production runs early next
year.
WBS 8.0 Education
and Outreach (Greg Snow –
The Auger Celebration
On November 9-11, 2005 the Auger Collaboration hosted a major Celebration marking the progress of the Observatory and the presentation of the first physics results at the International Cosmic Ray Conference in the summer 2005. Over 175 visitors from almost all of the collaborating countries traveled to Malargüe to attend the Celebration. The visitors included administrators from collaborating institutions, representatives from funding agencies that have supported the Observatory, representatives from the Argentine embassies of collaborating countries, local and provincial government authorities, plus press and media teams.
The program of the Celebration began with a
welcoming
reception the evening of November 9 in the
The Celebration was covered extensively in newspaper, magazine, and television pieces that appeared in several of the collaborating countries, and an article will appear in the CERN Courier in an early 2006 issue.
The Collaboration is indebted to the Observatory
staff and
the
The Auger Science Fair
The Auger Collaboration sponsored a Science Fair
for teachers
and students from high schools in
First place:
“Aerodynamic Wind
Tunnel” by a team from Escuela 4-106 “IV Brigada Aerea” in
Second place:
“Technological
Proposal to Address Pollution in the El Nihuil Lake” by a team from
Escuela
4-044 in El Nihuil,
Third place: “Magnetic
Levitation
Train” by a team from Escuela 4-106 “IV Brigada Aerea” in
Honorable Mention: “Calcium Sulfate Mill for Agricultural Use” by a team from the Instituto Secundario Malargüe
During the Science Fair, participants were treated
to
presentations about the Observatory given in the
The collaboration is indebted to the Observatory
staff, the
local organizing committee, Sra. Verónica Bunsters, and the
Premier Viewing of New Auger-Related Videos
On November 10 and 11 at the Convention and
Exhibition
Center, Malargüe students and adults were treated to the inaugural
viewing of 2
professionally produced video presentations directed by Christina
Raschia in
collaboration with Beatriz García. The first, “Space Messengers”, is
intended
for children aged 6-11, and the second, “An Adventure of the Mind”, is
aimed at
children over 12 and adults. The videos are in Spanish with English and
French subtitles
and are available through the
On Friday, November 11, a group of Auger collaborators and Celebration attendees visited the nearly complete new building that will house the James Cronin School of Communication, Art, and Design. Also in attendance were the building’s architect, the school’s headmaster, and a representative from the Mendoza Province Board of Education. A photo of the building appears in the gallery. The school is foreseen to be complete in time for occupancy when the new school year begins in March 2006.
On November 14, Rebeca López presented a workshop
on
teaching practices in the natural sciences to a group of teachers from
Malargüe’s
WBS 9.0
Observatory Operations – (Julio Rodriquez Martino - INFN)
During October and November some DAQ and Slow Control problems continued to affect the FD data taking. The problems in the DAQ are, in principle, understood but not yet solved. The
solution seems to be a change of the mirrorPCs, by some new pieces of hardware. Exactly what is producing the problem of the mirrorPCs dropping from the DAQ is not yet clear.
Another software for the analysis of the relative calibration runs was installed in the EyePCs. This compliments the analysis program described in the last report by giving the shifters a "snapshot" of each camera in the FD. It is possible to recognize and report problematic pixels
immediately. In addition, a routine analysis of the background measurement is in preparation. This will allow a better estimation of the dead time in each telescope, including times when the shutters close by external factors (rain, snow, wind or light)
The system of volunteers for the Fd shifts will be changed, as agreed during the last meeting in Malargüe. A proposal will be soon circulated among interested people and a decision
taken, hopefully before February next year.
Apart from some lightning storms and power cuts, the data taking shifts were succesfull, with many hybrid, stereo and three-eye events.