Summary (photo
album link)
The telescope in bay 4 of Los Leones is fully operational.The
bay 5 telescope requires only the completion of the shutter and a safety
curtain.The telescope is bay 3 is the next to be completed.Bay 3 overlooks
the surface detector stations being installed during the austral winter.The
first production PMT/head electronics units are under test.
Detector tanks are now arriving regularly from both
Alpina (Brazil) and Rotoplas (Argentina).Liners
are now successfully being produced at UTN, Mendoza.The
limitation on deployment has now shifted to assembly, water delivery and,
of course, the winter weather. The surface detector crew has been increased
to allow simultaneous station assembly and deployment.A
total of 70 pre-production tanks have been deployed.A
plan has been prepared for the deployment of the next 200 stations.
Surface detector PMT/base assemblies are in production.A
successful Production Readiness Review has been carried out for these assemblies.Five
production electronics packages have been deployed making these pre-production
stations operational along with the Engineering Array.A
run of defective printed circuit boards for the front-end electronics has
slowed the assembly and installation of more electronics packages.We
nevertheless expect to have a large part of the pre-production detectors
instrumented in July.
The micro-wave link has been successfully established
between Coihueco and the Auger Campus.The
radio system has been expanded to accommodate the increasing size of the
array.Construction of the Los Morados
tower has been initiated.The timely
completion is important since the eastern edge of the array now planned
for deployment comes under the radio coverage of the Morados tower.
Life at the Observatory has become easier with the
commissioning of a 1 Megabit/second internet link.
WBS 1.1 Fluorescence Detector – (Jonny Kleinfeller
– Karlesruhe)
Los Leones
Telescopes are installed in bay 4 and bay 5. Both
telescopes are equipped with the original prototype cameras and uv-filter,
new aluminum mirrors, new electronics and mirror pc, new aperture box and
new shutter. Both telescopes are in an enclosed in the new dust protection
curtain.
Telescope 4 has a corrector ring installed, and is
protected by the new type of emergency curtain. The shutter is fitted with
a motor and motor electronic, curtain and shutter are integrated into SCS.
Telescope 5 has no corrector ring installed, instead
a mask of 2.2m diameter is installed at the position of the corrector ring.
There is currently no motor, no motor electronics and no curtain for telescope
5, i. e. telescope 5 is not protected through SCS, and can't be operated
remote controlled.
SCS is pre-configured to operate curtain and shutter
in bay 5 as soon as they are installed.
The new low and high voltage system is integrated
into SCS, but operation of the prototype cameras requires the use of the
old low voltage system to provide sufficient current, the latter is not
controlled by SCS.
The parameters of the lv and hv system can be monitored
by SCS, but can't be modified by SCS.
DAQ is currently for experts only, there are some
problems with the initialization of crate parameters, and communication
with the calibration pc.
There is currently only the calibration fibre in the
centre of the mirror installed (script A). the fibres to the side of the
camera (script B) and to the screen at the shutter (script C) are missing.
The screens are mounted in bay 4, 5 and 3.
The shutter and aperture system of bay 1 at Coihueco
has been installed at bay 3 at Los Leones, the aperture box is aligned,
the shutter is sealed, the box not yet. the temporary window closure has
been removed. A filter is ready to be mounted.
The mirrors of bay 6 will be moved to bay 3 at the
beginning of June.
I plan to run a few nights with telescope 4 and 5
in the first week of June. Regular shifts could be scheduled for the end
of June and the following dark periods, if we get motors and curtains in
June.
There is a problem with the microwave link at Los Leones, it trips whenever the equipment is exposed to the sun (usually from 11 am to 6 pm on a sunny day). If the system deteriorates, we may not have a link at night.
Paul, Antoine, and Ruben are aware of the problem,
but there is no spare.
WBS
1.2FD digital electronics and readout
system – (M. Kleifges – FZK – HPE)
Installation
work in Los Leones (LL) and Coihueco (Co)
N.
Barenthien (IEKP- KA) installed during April 03 the Slow Control (SCS)
components for telescopes # 4-6 in LL and # 1-3 in Co. He was actively
supported by George and Primo (UTN San Rafael and UTN Mendoza): nearly
all prototype SCS cabled had to be remove and replaced (LL), the complete
cabling was missing in Co. Unfortunately, at the time of installation there
were no shutter motors and safety curtain present for connections and tests.
In a later stage, when the UPS and the shutter motors had been moved from
bay 6 to bay 4 (LL) the movement of the first ‘new’ shutter under software
control was verified.
Also
in April N. Kunka (IPE) upgraded the LAN in LL for all 6 MirrorPC and the
connection for the HV crate and the new GPS clock. As a result of a joint
effort of him, Ruben and P. Clark now LAN and internet access is also possible
to/from Co. S. Menshikov and myself installed the front-end crate for telescope
# 4 (LL), tested the hardware and connected it to the camera. Before we
left Malargue, the recently developed method of calibration with a LED
was tested and we verified that the brightness is sufficient to illuminate
all telescopes through fibres with one central source in the calibration
room. We also opened the shutters and tried to record showers, but we failed
due to a bug in the readout software. The commissioning continued with
telescope # 5 by P. Privitera in the same week. The measured values of
noise were comparable with the prototype or slightly better.
In
the following week H. J. Mathes found several (minor) other bugs in the
readout software, which were either related interface changes with the
hardware or with software changes to allow readout of several mirrors.
Most of the problems were found and solved. With some tricks even a dual
mirror readout was possible. However, within the next month the software
has to be made more robust and user-friendly.
Following
the decision to continue the installation with telescope #3 in LL, Primo
Vitale begun with the SCS installation of terminals in bay 3. Missing components
will be sent with the next transport or can be taken from (not used) Coihueco
bays.
Production
and tests in Karlsruhe
At
present, staff in Karlsruhe is testing 3 more front-end crates in the climate
chamber. These crates will be sent with the next air freight to Malargue
mid of June. The delivery will contain also GPS clocks, which are currently
specified by the Besancon group (F. Meyer). We are preparing the installation
of 2-3 systems (telescope #3 (LL) and # 20,#21 (=Co bay 2,3) ) around July/
August 03.
The
production of 132 more FLT boards (around 6 crates) is in the pipeline
of the IPE production centre.
SD
LED controllers
120
(more) controllers are tested and currently coated by an external company.
They will be sent to Jim Beatty in the first week of June.
WBS 2.1 SD (I. Allekote – Instituto Balseiro)
Site issues
A new surveying Differential GPS equipment was purchased
with fund provided by Chicago University. The equipment includes 6 handheld
GPS units, 2 laptop computers and a variety of accessories for fied work.
Detector deployment
More technicians have been hired for assembly and
deployment. The local long-term A&D crew is now composed of Ulises
Padroni, Fernando Olivera, Jesica Velazquez, Lucas Muñoz, Blas Ramirez
and, mainly for water plant operation and water related issues, Pedro Barraza
(3 days a week). Another technician, Miguel Salvadorez, will join the team
in June. An industrial chemist, Roberto Argumedo, is assisting in water
plant issues (efluents, upgrade, operation, documentation).
Tank production
Modifying the rock-axis hydraulic drive after its buckling failure; anchoring the doors at their open position; installing controls, including temperature sensor; installing air draft dampers and control knobs; mounting the tank spider on the axle.
It is expected that they will be able to produce the first prototype tanks sometime in June.
Rotoplas in Buenos Aires has produced a series oftanks
which were shipped to Malargue, and assembled and deployed in the field.
Some corrective actions still have to be implemented. Some problems in
their tank manufacture are:
- the lifting lugs are not correctly filled, so a post-molding filling is done. A poor bonding causes a gap between the filling and the tank and some show lightleaks at this point.
- some hatches have a large conicity which makes it difficult to attach
the hatchcovers correctly.
- thicknesses are not homogeneous and in some cases below specification.
Rotoplas is working on a solution to these problems.
Two prototype tanks made with fiberglass reinforced
resin technology were delivered to Malargue by Petroplast, for testing
purposes.
Liners and PMT enclosures
Liner production passed several milestones this reporting
period.The UTN Mendoza liner assembly
facility was completed, commissioned, and passed air quality test requirements.Assembly
of liners began at the end of April, and looks on track to meet or exceed
planned assembly rates and quality requirements.Training
for the rest of the production steps will occur in June, at which point
the facility will be completely operational.
Production of liners at CSU has stopped after producing
65 pre-production and 150 production liners and 1700 liner tops (all the
tops for all pre- and production liners).~110
pre-production liners and 110 CSU production liners are in Malargue now.
A small-scale prototype of a new IR-light based leak
detector has been tested at UTN, and it looks very promising.This
leak detector could eliminate the necessity of light leak testing in the
dark, greatly reducing costs and improving quality.
Sample replacement thermal insulation rings were made
by a vendor from Buenos Aires, and will be tested in PMT units in June.
All PMT enclosure components (except for the PMT alignment
collars) have been approved by the SD/SDE groups using them, and are currently
being produced for all 1600 production tanks.The
PMT collar mold may want one more mold modification to better fit the PMT
neck now that the dimensional tolerances are closer to specification.This
will be decided on after the PMT review in June.
Sensors
Pure Water
The water plant was shut down during the summer holiday
period. In February the plant was turned on again, without major difficulties.
The EDI output is stable at 11-12 MOhm-cm, a value which is below specification.
High quality water (resistivity above 15 MOhm-cm) is achieved with the
mixed resin bed.
The UV lamps at the water plant were replaced, as
their lifetime had expired.
TOC measurements were performed at different stages
of water poduction and at the storage tank. The value obtained for water
which remained stored in the 50.000 liter-storage tank during the 3 weeks
of holidays in summerwas below 100
ppb (sensitivity limit of the measurement). At the output of EDI, of the
mixed resin bed and of the UV lamps also yielded less than 100 ppb.
During April, bacteriological contamination was found
in one of the transport tanks (Tk-12-Alpha). The bacteria level in four
of the deployed tanks was higher than usual (the most contaminated one
had around 5000 colonies/100 ml). These tanks are being monitored and up
to now no bacterial growth has been detected.
Water delivery
WBS
2.2. Surface Detector Electronics (T. Suomijarvi – IPN Orsay)
Station electronics
SDE-Fabrica
will be in operation in the end of June. The assembly of the electronics
+ various tests will be performed in the Fabrica. SDE task is currently
discussing with the Mendoza group to have a person (Mariela) to superviseSDE
operations in the Fabrica. Some help from Auger students is probably also
needed later this year for SDE assembly and testing on site. In addition,
the SDE task will probably hire a second technician when reaching the full
operation mode on site. SDE task has bought a truck for the SDE installation
and other transportation on site. Wuppertal
group (Karl Heinz Kampert and his colleagues) has joint the SDE task. They
will be involved in fabrication of the FE boards and are currently applyingfunds
for this sub-task. Athens
(Emmanuel Fokitis and his colleagues) is looking into having funds to fabricate
the micro TPCB. Water level sensor
SDE commissioning
A list of monitoring and study items for the pre-production
will be prepared and tasks will be appointed for SDE + analysis groups.
Priority should be given for commissioning. A report on the baseline performances
will be written and discussed in a “SDE commissioning meeting” (Sept-Oct).
Only after the SDE commissioning is completed a “green light” will be given
for Physics.
SDE long term strategy
SDE installation
WBS 3.0 Comms Task (P. Clark – Leeds)
SD Wireless LAN Radio Reliability
Radio Link Quality. A brief analysis of a typical
day showed an estimated bit-error-rate (BER) of 1.3x10-8 from a packet-error-rate
(PER) of 2.7x10-5. This compares favourably with the design limit of 1x10-6
BER, 2x10-3 PER. However, note that we do not yet have any fully-loaded
base-station sectors or long-range links. All this will change in the next
few months!
Bugs. We think we still have a few ‘funnies’ in the
system. We seem to be suffering 1 second long data loss events from the
tanks a few times/day. We are working with the CDAS team to try to isolate
and eliminate the problem.
Los Morados Tower
Los Leones Tower
Coihueco Tower
The microwave link to Coihueco was installed, commissioned
and certified during this trip. The 38.7 km link shows excellent signal
quality and should prove to be highly reliable.
Coihueco Tower (cont.)
The IP link over the microwave system has been installed
and is undergoing commissioning and testing now.
The first wireless LAN sector has been connected and
will be brought fully into service during the next trip (November).
Surface Detector System Range Test
Surface Detector Antenna Alignment Utility
A software utility has been produced at Leeds that
automates both the surface detector antenna alignment and base-station
allocation procedures. This utility was written by Pete Walker and is installed
on the comms monitoring PC in the CDAS room.
The deployment team radios in their GPS co-ordinates
and the serial number of the SU radio to be connected.
The co-ordinates are entered into the utility, which
then returns the tower to be used for that tank, together with the compass
bearing from the tank’s position to that tower.
The utility also returns the correct base-station
sector to be used for that tank. The tank can then be connected, simply
by entering the serial number of the radio into the network list for the
appropriate base-station on the network monitoring PC.
Once the antenna is fitted and aligned and the GPS
timing is stable, the radio will connect the tank to CDAS automatically
via the correct tower and base-station.
V4.1 Wireless LAN Radio Production
Subscriber unit production proceeds approximately as planned with some minor niggles (now solved) causing us a 2 month slip earlier this year.
320 radios are now available at the campus (as at
15th May 2003). An additional 440 radios will be shipped during
Aug/Sept.
SU production Schedule
|
|
Batch
|
Total
|
|
On-site now
|
80
|
80
|
|
Just Arrived!
|
240
|
320
|
|
Aug / Sept 03
|
440
|
760
|
|
Dec 03 / Jan 04
|
440
|
1200
|
|
Apr / May 04
|
460
|
1660
|
|
August 04
|
Balance
|
1800+
|
IP Routers
Rene Bihaut will be installing the ‘big router’ at
the campus in the next few months. This will complete the campus shelter
IP installation and will terminate the ‘backbone network’.
Surface Detector Antenna Deployment
This task has been successfully handed over to the team led by Jorge Abraham of UTN Mendoza.
Jorge’s team are working on deployment documentation, which we will integrate into the EDMS system in due course.
UB-Comms Integration
WBS 8.0 Education and Outreach (G. Snow – University
of Nebraska)
Short Course for Malargüe Science Teachers
Visitor Center Virtual Web Site and Visitor Statistics
The week before the collaboration meeting, Beatriz García and Greg Snow met with the Mendoza-based team of professional web designers, Antonio Castineira and Alejandra Cicero, who demonstrated a nearly-final version of a web site designed to provide a virtual visitor experience to the Auger campus and the Observatory. The web site presents images of the campus and Los Leones, excellent animations of air shower development and detection, directions to Malargüe and the Auger Visitor Center, and highlights of other attractions in the region. A few remaining items will be implemented or refined before the site is made available for collaboration comments and its eventual link to the Auger home page.
Planetarium Milestone
On Friday, March 21, a truck which arrived in Malargüe
with 6 SD tanks from Rotoplas was loaded with two Mexican prototype tanks
destined for the Eureka science museum in Mendoza. These were delivered
and unloaded at Eureka late that night. The two tanks are now located outside
the main exhibit hall and photos appear in this month’s Photo Gallery.
UTN-Mendoza staff will be outfitting the Mexican tanks with solar panels
and antennas. The week before the collaboration meeting, discussions continued
with Eureka director Lilia Dubini about the opening of the Auger exhibit
which is now scheduled for Saturday, November 22, just after the next collaboration
meeting. Greg Snow advanced funds to Eureka to start production of 4 self-supporting
stands which will enclose posters outside the main hall and 7 frames for
posters inside the museum. The poster graphics will be done by Eureka staff
with content input from Auger physicists.
Meeting at CNEA Headquarters
On Monday, May 5, Greg Snow
met with the CNEA director of communications and public relations, Lic.
Luis A. Jolivet, and other staff members at the CNEA headquarters in Buenos
Aires. They shared ideas on public outreach activities in Mendoza Province
and throughout Argentina related to the Auger Observatory and other CNEA
initiatives, and they agreed to a continued collaboration.
Buenos Aires Television
Program on the Observatory
Ing. Antonio Tersigni and a
2-person camera crew visited the Observatory on Thursday and Friday, May
1 and 2. Tersigni produces a weekly morning television program entitled
“Mateando con la Ciencia”. Tersigni and crew took extensive video footage
of the campus and Los Leones and interviewed several Auger collaborators
including Arnulfo Zepeda, Rebeca Lopez, Alberto Etchegoyen, Jim Cronin,
and Greg Snow.
Michigan Technical University Scholarship
The first Malargüe student, Angelo Chialva, enrolled
at MTU under its Malargüe scholarship program is a continued success
story. He has completed his first two years as a mechanical engineering
major. He was a member of the MTU team participating in the nation-wide
Ford Future Truck program which won 2nd prize in the 2002 competition
to redesign the Ford Explorer for improved fuel efficiency and performance.
The second scholarship recipient will enroll at MTU in the autumn 2003.
Two finalist candidates have been identified via their physics and math
test results, and the selection of the scholarship recipient will be determined
when their TOEFL exam results appear in June. David Nitz and Greg Snow
met with the parents of the two finalists during the collaboration meeting
to answer their questions about the MTU program.
Auger Poster Competition
A competition was announced within the collaboration
in February to produce a single, striking poster about the Observatory,
translated into many languages, for wide distribution – to funding agencies,
science museums, etc. Six entries were submitted at the collaboration meeting
and collaborators were invited to vote on the best poster. The entries
can be viewed in this month’s Photo Gallery. The results of the competition
will be announced to the collaboration shortly.