Pierre
Auger Project
Progress
Report
Summary (photo album)
The continuing operation of the 18 telescopes in the three FD buildings has resulted in a marked increase in the number of valuable hybrid events and even a few triple stereo hybrids. Corrector rings for all of these telescopes have been finished and last of them are on the way to Malargüe.
Deployment operations are back to normal (for the winter) after an 80 cm show fall in late August. The delivery of tanks from the new Brazilian vendor has begun. The new tanks are of high quality at an attractive price. A combination of funding shortages and the process of qualifying the new vendor had until recently brought the delivery of tanks to stop. Deployment is moving steadily, if slowly, to the areas accessible this time of year. Agreements with land owners are being made just ahead of our need for more deployment sites. A recent milestone was reached with the deployment of 800 E-kits. A major activity is maintaining the supply of components for the final push to complete the array in 2006.
An intense effort is underway in the FD groups to resolve a verity of software problems that have slowed data taking and calibration runs. The most intractable of these problems is a communication problem between the mirror PC and the camera crate and has proven extremely hard to locate. Resolving this problem has the highest priority.
Surface array data taking operation including the communications system and CDAS has also been unstable for the past few months. This instability together with a small but continuing rate of failures in the field has reduced data taking efficiency.
Now that the analysis of the first data set and presentations at ICRC 2005 are behind us, we intend to make a determined effort to put the data taking operations on a smoother, more efficient footing. This effort will necessarily require a greatly increased participation in the observatory operations by the members of the collaboration.
Plans for the Auger Celebration are developing
well. The activities will include a
reception on
the evening of 9 November, a symposium, monument presentation and asado
on 10
November, tours for our guests and a science fair on 11 November and
the
inauguration of the
WBS 1.2 FD
digital electronics and readout
systems (Matthias Kleifges – IPE)
Progress
of the Slow Control System (SCS): (by
K. Daumiller)
During the
recent month there were a lot of smaller changes and bug fixes in the
SCS, even
though these are not visible to the user. The most important points are:
·
Starting
from the next shift (September 2005) the shift crew will hear an audio
alarm in
case the SCS is changing the operating state to fulfil safety
requirements.
Thus the crew is aware of closing shutters due to increased wind speed
or
falling rain and switched-off HV due to over-voltages, over-currents or
light
inside the bays. The software will be installed; Primo and Ruben have
already
wired the loudspeaker in CDAS.
·
The
·
A
watchdog plug-in PC card is in use to monitor the SCS activity. In case
of a
hung-up of the SCS FieldPC the watchdog will enforce a secure state of
the SCS.
Our experience shows that the FieldPCs are not as reliable as expected.
We are
therefore looking for alternative 19” PC (with standard components) as
long
term replacement.
·
Kai
fixed other minor bugs, especially to improve the communication with
the CAEN
HV main frame. The HV systems frequently reports fake channels in
current
overflow, a problem under investigation by the
·
The
program Quickmon parses through logfiles of the DAQ and displays
current
trigger- and hitrates of the telescopes in the DAQ chain.
·
A
main new release of the SCS is going to be installed in November, but
bug fixes
are implemented on a smaller time scale.
Progress
in DAQ and related software: (by H.J.
Mathes and A. Kopmann)
The DAQ and
related software undergo permanent improvements and bug fixes. Most
important
changes are:
·
Defects
in the former build system (based on intake) forced investigations of
alternative build systems for the FD DAQ software. We have selected
(and since
late May 05 in use) the scons build system (www.scons.org)
which however made a complete change of every line of the former
Makefiles/Imakefiles necessary. The packages of the FDEventLib are now
been
built using the GNU autotools systems – the same as used by the AUGER
Offline
software.
·
Circular
dependencies in the FD-DAS source tree have been found and resolved.
This lead
to a new name in the CVS repository: FD-DAS3.
·
Bugs
in the communication interface FD-T3 to LIDAR/CDAS have been corrected.
Both
communication interfaces are now identically implemented, asymmetries
have been
removed.
·
An
alternative variant to veto bursts of trigger signals is implemented.
·
The
compressing and archiving of log files is automated to avoid wasting of
disk
space.
·
Some
bugs in the online systems are fixed as described in the ELog book.
·
At
the end of 2005 there will be the next leap second. The routines for
time
conversions are updated by an extendable table to reflect this change.
·
The
FDEventLib v2r7 was released. We have announced a new version v3r0 to
be
released soon, which will include fields to account for DAQ dead time
and
vetoed triggers as well as a new format of SLT multiplicity data.
·
The
access of the DAQ to the GPS clock was changed to allow reprogramming
of the
GPS gate generators through users without resetting the DAQ.
·
The
most severe problem of the DAQ is an unsolved communication error
between the
MirrorPCs and the FD sub-rack on the FireWire (FW) link. The problem is
encountered frequently on site during calibration, but also seldom
during shower
recording. Normally the communication of individual telescopes stops,
the
telescope falls out of the DAQ and the MPC has to be rebooted. The
problem was
also found on the test system in
·
The
Auger hardware library fdhwlib was revised to separate Auger specific
functions
from more general functions. The objective is to implement an interface
which
defines the data to be exchanged together which the data structure. In
this
way, the library can be used for other experiments using the Auger
front-end
cards (like KATRIN) as well.
Progress
in Calibration routines: (by A.
Menshikov)
Up to
recently calibration data was recorded each night, but not analysed on
side
instantly.
Since the
August 2005 shift the SW package called Calprog is installed on all FD
sites.
The package consists of several routines to
a.)
perform
prompt tests of all electronic channels using the electronic test
pulser,
b.)
measure
the current gain ration between normal channel and virtual channel, and
c.)
analyse
the data recorded by relative calibration A, B and C. For each
calibration the
relative gain is calculated (at different wavelength or amplitudes for
the
Xe-flasher system) and saved in a set of files, whose structure and
format is
published in a recent GAP note and approved by FD calibration community.
d.)
Special
programs analyse the data recorded by the drum and propose changes in
the HV
settings and the electronic gain settings in order to achieve a flat
field response.
The
routines were successfully tested at the end of the August shift and
allow the
crew to recognise FD hardware failures (PMTs or front-end boards)
before the
data taking starts.
Other
activities:
IPE and IK are developing a balloon- born light flasher which
will
provide an independent test of the telescope alignment and calibration.
A first
version of the flasher was tested (see report of March 05)
successfully, but
the intensity and wavelength of the LED lamps will be changed with a
new
design. We also plan to equip the next flasher version with a Motorola
GPS
module (replacing the module coming with weather balloons) and transmit
the
flasher position to ground by radio.
WBS 2.1 SD (Ingo Allekote – Instituto Balseiro
and Meter
Mazur - Fermilab)
Routine production of water tanks for surface
detectors at
Rotoplastyc in
Resin for about 100 more tanks is now in
Detector deployment and commissioning has been below expectation in
this period
due to the unavailability of tanks. 48 surface detectors were deployed
in the
field, 58 were filled with water and 46 were equipped with E-kits. To
achieve
this, most of the Engineering Array tanks were recovered from the field
and
refurbished. All recovered EA tanks could be re-used for the production
stage.
WBS 2.2 Surface Detector Electronics (Jim
Beatty –
A significant milestone was recently passed with deployment of the 800th E-kit. As of the time this report was prepared, 826 tanks were taking data.
The major activities at present are maintaining the supply of components arriving in Malargue to support deployment, addressing problems with the system as they arise, and making the transition to the use of front-ends from the Wuppertal-Siegen-Aachen groups and TPCBs from the Dutch groups.
The new Cyclone-based front end successfully completed a critical design review at the June analysis meeting, Procurement of long-lead time components is now underway, and ten prototypes of the final design will be completed in early September. 100 preproduction boards will follow in October, with the full production to follow shortly thereafter. The German groups have kindly agreed to fund production of 100 additional boards of the original design to ensure continuous availability of front ends for deployment.
A first batch of Dutch TPCBs has been completed and is now being tested. Once testing has been completed, production of the remaining TPCBs for the full array is expected to be completed rapidly.
We congratulate the PMT test leader in Malargue,
Federico
Suarez, who has obtained a fellowship from
WBS 3.0 Comms (Paul Clark –
Deployment of antennas and preparation of antenna kits has continued well with the deployments passing half-way (>800 tanks) recently during this period.
Surface Detector Antenna System preparation and deployment - Jorge Abraham
- 25 Kits were mounted during June 2005 and 33 during July 2005.
- There are 216 Kits ready to install. Total prepared: 1124
- Antennas for more than 120 Kits were tested.
- 913 antennas have now been mounted. (Rate ~ 44/Month)
- The last 70 Antennas will arrive on-site During August.
- Stock of some loose parts for the antenna kits has reached zero in Malargue and no more kits can be prepared at the moment. These parts should be on their way from the US in the next few weeks. Note that, there are a large number of prepared kits (200+) available so this shortfall should not affect deployment.
Surface Detector Antenna System Commisioning and Maintenance – Jorge Abraham/P Clark
- Antenna reorientation plan and the UV protection programme. We are working altogether with the Observatory tasks groups. This is SD, SDE, Water. They include it in their tasks to the field.
- A recent new task for Jorge is to monitor the quality of the radio link established to any newly deployed tank. If the link quality is poor, he has a number of remedial options open to him; the simplest of these is to try the tank on a different BSU sector.
Jorge: "I make a control periodic of the SD Signal quality. Later I indicate the changes to make to solve the problems.
In these conditions, from the first analysis, we have corrected more than 6 SD-Signal with no need to go to the field to do it. (Configuration SU/BSU was modified only)."
This essential task is now well under control.
- Antenna reorientation tasks will be undertaken in the field during
August.
Comms Upgrades
We have been trying to get some new NetMon PC Servers* to the site since March. We have finally been successful and the equipment is now in transit to Malargue. The current machine is thoroughly overloaded and unstable and is preventing us from doing other comms software upgrades. Once it is intstalled we can move forward again with other upgrade work.
*These machines control and monitior the comms radio network.
It is likely that all the final comms components will arrive in Malargue during the next period.
WBS 5.0 DPA/Offline- (Bruce
Dawson, Markus
Roth and Tom Paul)
This period was a busy one, with most effort
concentrated on
the analyses presented at the ICRC. Contributions were made by many
people to
the energy spectrum analysis, to the photon upper limit analysis, and
to
characterization of the detector aperture and reconstruction quality.
The Offline framework worked well for all this work, and we are
continuing to
work on improvements. Apart from continued improvement and bug fixing,
our
major software thrust before November is hybrid
simulations/reconstruction,
with particular reference to the elongation rate and photon limit
studies. After several false starts, we are also getting underway
with
production runs of fully simulated SD events.
The core framework is undergoing further extensions and optimizations.
A 10 day
software meeting has been scheduled for October, to be hosted by CBPF,
and will
give the developers an opportunity to work together on some of the most
important framework issues.
The aerosol and atmospheric quality databases have been populated, and
high-level interfaces for access to these data are currently in
preparation. Information on station positions and
deployment times have been moved from static files to a database, so
users will
have information on new stations soon after that information appears in
the
PMS. Two new Fermilab personnel (Paul Lebrun and Patricia
McBride) have
also joined the experiment and are planning to contribute to the
offline
code. We are currently working with Paul to set up a master
database mirror at Fermilab.
WBS 9.0
Observatory Operations – (Julio Rodriquez Martino - INFN)
Problems
with DAQ hardware continued during this period. Los Morados was
especially
unstable, which is clear from the very short runs available in the data
set.
Problems will be hopefully solved soon, since H-J. Mathes, from
Data quality is regularly reported by using an off-line filter and other tools. The description of these tools can be found in:
http://calib.auger.org.ar/quality/general.html
The results of the analysis are available at:
http://calib.auger.org.ar/quality/FD_quality_reports.html
Volunteers are needed to regularly look at these data, evaluate the quality of the FD events and the general status of the telescopes. It could be useful to implement a system were different institutions take turns to analyse the data and report their results.