Pierre Auger Project

Progress Report

 

July & August 2004

 

 

Summary (photo album)

 

The third fluorescence building at Los Morados is now complete.  The building turned out very well in spite of construction difficulties caused by its remote location. Due to shortage of funds, however, Los Morados still lacks heating and air conditioning equipment.  Telescope installation is nevertheless proceeding with the help of some (rather inadequate) temporary heaters.  Preparations are moving ahead on the bidding process for the last fluorescence building at Loma Amarilla. 

 

The twelve telescopes at Los Leones and Coihueco are in stable operation and are recording large numbers of hybrid events.

 

Intense effort continues on the calibration and atmospheric monitoring systems. The Central Laser Facility now has both fixed and steerable lasers in remote operation.  The Lidar system at Los Leones is in routine use and the one at Coihueco is nearly complete.  

 

As springtime weather approaches deployment of surface detector stations is accelerating.  There are more than 535 detector tanks deployed with 450 of these taking data.  Because of exceptionally low water levels, our determined deployment crew has been able to install tanks in a seemingly inaccessible location between the Atuel and Salado rivers near Coihueco.  The current deployment is concentrated in the area below the Coihueco fluorescence building with the objective of further augmenting our set of hybrid events.

 

Short term funding for surface detector components remains an acute problem.  We currently have a sufficient number of components to assemble surface detector stations only through the early months of 2005. 

 

 

WBS 1.1 Fluorescence Detector Calibration (John Matthews – University of New Mexico)

 

The installation of the optical fibers for the xenon based "B" and "C" calibrations at Coihueco was completed August 14, 2004.  Thus "A", "B" and "C" (relative) optical calibrations are now available for all 12 operational telescopes (at Los Leones + Coihueco).

 

WBS 1.1 Fluorescence Detector Atmospheric Attenuation (Mike Roberts – Utah)

 

Atmospheric monitoring

The CLF solar power system was upgraded in August. The CLF is run routinely during FD data taking and data analysis is progressing

The Los Leones LIDAR is also being run routinely during FD data taking. At present only "local scans" of the atmosphere are being made. "Shoot the shower" scans will be implemented
when a new laser becomes available.

At the Coihueco LIDAR the board that allows the FD to trigger the LIDAR arrived from Karlsruhe in August. This will be installed in September by which time the LIDAR should be ready for use.  
The LIDAR concrete pad and power are completed at the Morados site. The LIDAR container is in Mendoza being modified and the LIDAR steering mechanism is in Malargue. The Morados LIDAR steering mechanism will be installed before the November meeting. Start of operation for this LIDAR will be determined by the availability of a laser,

 

 

WBS 1.2 FD digital electronics and readout systems (Matthias Kleifges -  IPE)

 

Progress in Slow Control software (by C. Wiebusch, Uni Wuppertal)

 

·        In the previous bi-monthly report we have reported the problems in the communication between the slow control system (Windows) and the DAQ (Linux) based on the OPC protocol. The Wuppertal group has therefore setup a Slow-Control test system with a 4Control OPC server and installed/configured an OPC-XML-DA gateway on the same system. The group can successfully access OPC variables from the SC-PC with a small PERL test programs from a Linux-Client PC. The variable access was also possible from the Linux client by a C++ program using the QT-httpd interface. The group has already bought 4 licences for the Gateway software for installation on the SC-PC in each of the 4 FD buildings.

·        The next step will be the implementation of a reliable communication library for use by C++ client programs (diploma thesis of Martin Barkhausen) and the installation of OPC-XML-DA gateway on the SC-PCs in Los Leones and Coihueco.

 

Progress in DAQ software (by H.J. Mathes and O. Martineau, IK)

 

·        The improvements mentioned in the May/June report came into operation since the August shift. The associated version of the FDEventLib (v2r5) fixes a few bugs, but leaves the data format unchanged. We have also improved the functionality of the DAQ. With the next release (v2r6), which is going to be active from the September shift, the event data will include the last trigger time stamp and a quality parameter for the time correction.

·        A rare problem in the FireWire interface/Linux driver, which usually removes a telescope from the DAQ and requires a complete reboot of the telescope hardware, is still not found. This problem occurred twice in the August shift and it can be reproduced with a similar probability on the test system in Karlsruhe.

·        J. Matthews made several modifications in the scripts running during calibration on the CalibrationPC. Based on his suggestions a few modifications were also done on the DAQ side. They will hopefully fix the problems in the communication with the DAQ from the September shift.

·        The Run Control Software was modified to handle lost (no longer under control of the DAQ) processes which are present after DAQ crashes or handling errors of the operator.

·        O. Martineau tested the actual TLT software and discovered some inefficiency in case of very inclined showers. He also found events with a high number of triggered pixels which unintentionally pass the algorithm. This problem has already been fixed, but more tests are necessary before other changes in the TLT will be installed.

·        We are preparing the change-over from the current Linux version to SuSE 9.1 with kernel 2.6, which will take place in Malargüe in January 2005 with the installation of the RAID system as EyePC. As a first test we compiled successfully the complete DAQ package under the gcc 3.3.x compiler necessary with SuSE 9.1.  Everybody has to be aware that his software must soon be compiled this way, if it is running on the EyePC or MirrorPC.

 

Production and tests in Karlsruhe:

 

·        FLT: 463 FLT (89% of total) produced; about 420 are tested, sufficient for 21 telescopes.

·        LED controller: 791 controllers are tested and send for coating to an external company. They will be shipped in October 04.

 

 

 

WBS 1.2 Fluorescence Detector Electronics (Daniel Camin – Milano)

 

1)      Status of the PMT+HE debugging system: software development is virtually concluded. At present a choice of the most appropriate way to integrate the hardware, that includes also generation of test-pulses emulating the presence of the PMT, a small bar-code reader and an a DAQ board is in a definition stage.

 

2)      We are developing tools to extract stars signals form the FD background files. These tools are necessary to evaluate the absolute pointing of the telescopes at LL and Coihueco and soon also those of Los Morados. The working group is formed basically by collaborators of Milano and UTN-Mendoza. It is expected that in the next 90 days results will be available, at least those of  LL and some units of Cohiueco.  The knowledge of the absolute pointing of the telescopes with high accuracy is essential for a good reconstruction.

 

3)      Production of the HE’s has been completed. At present all instruments installed in Elbau, in Berlin, have arrived in Milan. The box containing 130 kg of instruments will soon be divided into instruments that will return to CERN and those that will be sent back to INFN-Milan.

 

4)      Besides the participation to the data taking in August, there was basically no activity during this month, which is normally used for holidays.

 

 

WBS 2.1 SD Site (Ingo Allekote – Instituto Balseiro)

 

During July-August 2004, a total of 158 tanks were received in Malargue, from Alpina, Rotoplas and Formingplast. One tank was damaged during shipment. Nearly 200 tanks are in the AB yard

awaiting assembly and deployment.

 

In this period, 60 new detectors were assembled, 82 were deployed and 62 were filled with water, 2 of which were filled by transferring water from EA tanks. 78 detectors got electronics

installed and started to take data. A total of 480 detectors beyond the Engineering Array have already been installed in the field. As of September 8th, 435 detectors are operational.

 

Due to the extraordinarily low level of water in the Atuel and Salado Rivers, it was possible to deploy detectors in the delta formed at the junction of these two rivers. The deployment teams

also started to deploy tanks near the Coihueco area, in order to obtain a large amount of hybrid events in a short time.

 

During installation of PMT's, one liner caught fire because the alcohol used for cleaning the dome had not dried out completely before activating the surface with the tesla coil. The fire was

immediately controlled and nobody was injured; safety measures were implemented to avoid similar accidents in the future.

 

A new purchase order for 200 battery boxes and pipes was placed at Formingplast, who is producing them and shipping them regularly to Malargue. Also, a new rotomolding company was contacted for battery box production and a new mould was ordered. The mould

has already been completed and the company has already made one good battery box.

 

A purchase order for 3000 kg of square tubing for brackets was sent to Aldural in Buenos Aires.

 

The seventh liner shipment with 110 liners arrived in Malargue on August 18th. Up to now, the liner facility at UTN in Mendoza has produced 813 usable liners.

 

At the new "galpon" for liner storage in Malargue, shelves were installed to allow storage of a larger number of liners. At present it can hold a complete shipment of liners, but the

galpon has space for storing the full future production.

 

One leaking liner was recovered from a tank in the field. Samples were taken and no contamination was found in the inside.

 

 The water plant operated without difficulties.

 

The fourth water transport tank was ordered and the company has already submitted the drawings for it, which are presently under revision.

 

Bacteriological analysis of the water in the transport tanks and in the detectors yielded the usual results, 35 without contamination and 7 with a very low quantity of aerobically bacteria,

probably due to contamination during sample taking.

 

Contracts for land access and permission for SD deployment have been signed with 5 more landowners. Also, the contract for the installation of the FD building was signed with the corresponding landowner.

 

WBS 2.2. Surface Detector Electronics (Tiina Suomijarvi – IPN Orsay)

 

The electronics deployment has reached the tank and water deployment rate. About 440 stations are currently taking data. The different electronic boards are being shipped to Malargue in large batches. The latest UB shipment was a batch of 486 units. No particular problem concerning the procurement and shipment of boards to Malargue is expected before the end of funding of the FE and the TPCB boards (after 800 units in the end of this year).

 

Activities in the SDE-Fabrica, PMT-House and deployment are running smoothly, thanks to the very highly qualified local staff. The SDE-Fabrica really looks now like a large scale factory (see figures)! However, more computers and laptops are needed for the SDE site activities. CALL FOR COLLABORATION: WHEN UPGRADING YOUR LAPTOP, THE OLD ONE CAN BE USEFUL ON SITE! PLEASE, CONTACT THE SDE TASK LEADERS.

 

Ignacio Rey (from UTN) is programming a new inventory system to be used in the SDE-Fabrica. There will also be a web page where everybody can access to see the actual inventory, failures, etc. This system will be compatible with the PMS (Part Management System) of the observatory. 
 

The LED assembly has been moved to Malargue. The soldering of the cable to the LED driver is done by Fabian and Javier in the AB (see figures). The potting is done by the group of Federico in the SDE-Fabrica (see figure). The flashers are tested before installation to the tank. For the moment no failures have been observed on the field. However, currently the flashers are used only in the installation and deployment. The plan is to implement the linearity test by the LEDs in the local station software in November and start post installation linearity checks. 

 

PMT testing and potting is catching up the Photonis shipment rate. The first PMTs with better linearity are currently being shipped. The ready-to-field PMTs are stored in a container (protected against heat) at the SDE-Fabrica and then transported to the AB in the same packages used in the Photonis shipment (see figures, and note that there was snow in Malargue during the first week of August when T.S. was there).

 

The PMT shipment rate cannot be increased due to funding problems. A new PMT master order (about 2000 PMTs still need to be ordered) is currently being placed by Jim Beatty (Ohio). About 1000 PMTs of this order will be funded by France through payment to common funds. Italy and Czech Republic have also considerably contributed in funding Surface Detector PMTs.

 

PMT testing in the AB after their installation will continue even though the failure rate in this test is small. This test gives a reference point for any later diagnostic of problems. Currently there are 3 Test Kits (Torino test kit), one of them is connected to a laptop. The test takes about 15 min per tank.

 

Concerning the dome that protects electronics on the tank hatch cover, the current method used to seal the dome (o-ring + foam for the antenna cables and solar panel cable) seems to be efficient. No dust is observed to penetrate inside the dome. Currently an ice protector ring is installed around the fez (inside and outside, see figure).

 

A rather large number of field failures were observed in the battery temperature sensors. The failures seemed to be due to non conform assembly and potting of the sensors. After a corrective action, these sensors are again being installed (since May 19). 

 

Concerning other failures in the field, 14 radios have been brought back from the field. Currently the reason is unknown. 10 Ekits were brought back from the field due to fuses. Currently there are about 27 PMTs on the field with unstable behaviour as a function of temperature. No clear cause has been found for this failure in spite of extensive tests in a temperature/humidity chamber at the IPNO. All the field failures are being carefully monitored by using BUGZILLA.

 

 

WBS 3.0 Comms (Paul Clark – Leeds)

 

After final selection of the FD/tower site at the July meeting, very good progress has been made on the final tower during the last 2 months.

 

Tower

A specification has been drawn up and the first quotation received. The soil survey of the ground is being conducted this week (Sept 6th) and work is ongoing to transfer funds to Argentina to allow placing of the purchase order for the tower. Time is tight but there is still enough time for the tower to be constructed in the next 2-month period as per schedule.

 

Tower Antenna System

The parts list has been drawn up, an order placed and 95% of the goods received at FermiLab. It is very likely that this equipment will be on site in time for the November deadline.

 

Microwave system

Jose Balacco has obtained a frequency allocation for us in record time and this information has been used to finalize a purchase order for the microwave equipment which is being supplied by the French. We hope that the order will be placed any day now and that there is still hope that the equipment can reach Malargue in time for the November 1st deadline.

 

 

Radio Manufacture

Another shipment of 240 radios has left Leeds and should be arriving in Malargue any day now, bringing the total on site to 1040 Subscriber radios

 

At Leeds, we are in the middle of our final production run of around 700 more to complete the requirement for the project. We intend to ship 380 more radios to site during October and we are still on target to complete all shipments by the end of 2004.

 

 

SD Antenna System Procurement

New UK funding has allowed procurement of the final batch of antenna system parts to proceed. Work is well advance on this task and all items should have been ordered by the end of September.

 

 

WBS 3.0 Comms continued (Ing. Jorge Abraham – UTN)

 

1) 37 Kits were mounted during July 2004, 26 during August 2004 and there are 226 ready to install. All antennas were tested too.
The 428 antennas of Pre-production and production were reached.

2) The Stock is fully controlled. We have all the quotations for the final purchase and 60 antennas in production.

3) The Anritsu test cable, has supported well its 4 measurements by Kit (more than 650 tests), but we do not know when it will be broken definitively.

 

WBS 5.0 DPA/Offline- (Stefano Argiro – INFN)

 

 

The Data Processing and Analysis task is successfully proceeding towards its two main goals:

 

1) Organize the analysis

2) Complete the integrated Offline framework for simulation and reconstruction

 

As for point one, progress was tangible at the Leeds collaboration meeting.

See Alan's email to the collaboration of 9/9 "some steps toward and SD analysis". Another highlight is the forthcoming workshop on anisotropy analysis, promoted by Antoine and Paul S. and taking place in Malargue, November 8 and 9. The FD analysis is working nicely toward a deep understanding of the detector and of the reconstruction algorithms.

 

As for point 2, the Leeds meeting showed that many groups carried out successful analyses using the Offline Framework. Although the "summer effect" prevented the Offline group to release a

1.0 version of the Framework, this piece of software has become fairly stable, allowing people to concentrate on physics issues.

 

The goal is to have complete simulation and reconstruction chains by the November CM.

 

Last point, the DPA School of computing will take place September 20-23 in Torino. The feedback of the collaboration  was very good, counting 36 registrations as of Sept 10.

 

 

WBS 8.0 Education and Outreach (Greg Snow – University of Nebraska)

 

On Tuesday, August 25, a signing ceremony took place to formalize the agreement between the Foundation of the Auger Observatory and the provincial government of Mendoza for the construction of a new building for the James Cronin School in Malargüe. The school will be constructed with funds provided by the Grainger Foundation in the U.S. and the government of Mendoza. Carlos Hojvat signed the agreement on behalf of the Auger Foundation and the Minister of Environment and Public Works signed for Mendoza. An article about the ceremony appeared in Mendoza’s Los Andes newspaper the next day.

 

On Wednesday, September 1, John Harton and Greg Snow attended a meeting of the Southeast Colorado Board of County Education Commissioners in Lamar, Colorado. Lamar is near one of the candidate sites for Auger North. John gave an overview of the observatory and Greg spoke about education and outreach opportunities that could link schools in the region to Auger North if it is located in Colorado. There was great interest among the commissioners who forwarded information to a list-serve of science teachers in the region. John and Greg are planning a second meeting with interested science teachers from the region before Christmas. Lamar Community College has agreed to host the meeting.

 

Preparations of displays and posters continue for the Auger Observatory display at the Open Day of CERN’s 50th Anniversary celebration on Saturday, October 16. The photo gallery of this report shows SD and FD detector models under construction in the University of Nebraska machine shop that will be elements of the display.

 

 

WBS 9.0 Observatory Operations

 

FD data operations – (Julio Rodriguez Martino - INFN)

 

 

The installation of the new calibration server was finished in Malargüe in the middle of August. The purpose of this machine (calib.auger.org.ar) is to have all FD calibration data in one

place and to analyze this data on site. A database will contain the results of the analyzed calibration files. Some details about the machine and its contents can be found in http://calib.auger.org.ar.

 

All calibration files existent is CDAS were moved to the disk array in calib. Raw calibration data is no longer mirrored in Lyon. Raw data will be backed up locally in tapes. The RAID system that holds the data has also a system to safely recover the data in case of a disk crash.

 

The Auger offline software was installed in the computer, together with the necessary databases. We still need software to analyze the raw calibration data.

 

There is also one month of minimum-bias data on disk, that can be used for trigger efficiency studies. The plan is to have the last 3 months of this kind of data available in calib all the time.

 

There are ongoing efforts to optimize the use of the available bandwidth and data storage.

 

Many thanks to Ruben Squartini who did most of the installation work and Stefano Argiro' and Tom Paul who helped with the offline and database installation.

 

 

The SOC responsibilities will now be divided between two scientists -one for FD and one for SD. Julio Rodriguez Martino will take care of the FD-SOC part.  Julio is resident at the Observatory and is sponsored by Rome. At the same time that he is carrying out the

duties of FD-SOC he will continue to help with the installation of the fluorescence telescopes.

 

A summary of the FD-SOC duties is found at http://www.auger.org.ar/FD/SOC-FD.html

 

The August FD shift was generally very successful. Some minor problems with the hardware and software were found and are now fixed.

 

A full shift report was generated for the first time from the DAQ log files and using the notes made in the e-log by the people in shift. This is an ongoing work that will improve in quality with time.

 

To see the report, go to the local FD page http://www.auger.org.ar/FD/

 

 

Starting from the September shift, there is a template form to help writing the e-log entries in an ordered way, easier to read and understand. A special e-log file is used only for the shift, separating its entries from the rest of the FD activities.

 

http://www.auger.org.ar/FD/fd_report.txt

 

 

At the time of writing this report, the September shift is in its 3rd day. After two days of bad weather, we had an incredibly clear night. At least 7 golden hybrid events were registered, one of which is also stereo. Thanks to the very professional shift crew and we hope to have many

more interesting events