Pierre Auger
Project
Progress Report
Summary (photo
album)
Another construction milestone has been passed. As of 11 May three quarters of the surface array (1200 detector stations) are now in operation! Deployment on the Villar land in the northeast part of the array is now finished. The weather has been cold but clear so that deployment on the Rufinelli land is proceeding at a rapid pace. We have only one parcel of land for which we have not yet obtained access. Negotiations are in progress.
There are 1689 tanks deployed or in the pipeline. We expect the last of the tanks to be at the Observatory ready for assembly by August. There are nearly 200 electronics kits ready for installation and the rest are expected to be ready in another two months.
All of the fluorescence telescopes are operational. A complete calibration is underway and should be complete by September.
The two enhancements that involve an infill array overlooked by telescopes that extend fluorescence coverage up to 60 degrees from the horizon are in the final stages of technical review. Plans are being made to include radio air shower detectors over all or some of part of the infill array.
Auger will once again be a major participant in the International
Cosmic Ray Conference with 35 talks and posters. The conference this year will be held in
WBS 1.1 Fluorescence Detector
cont. (Jan Ridky – FZU)
There are under way several analyses of FD calibration (yet not fully understood), new design for drum calibration and on negative side not running of Loma Amarilla due to late gas delivery.
WBS 1.2 Fluorescence Detector Electronics
digital electronics and readout systems (Matthias Kleifges
– FZK-IPE)
Software progress
·
During
his last stay H.J. Mathes has commissioned the DAQ
software for Loma Amarilla. At the same time also the
software for LL, Co and LM was updated to revision 3.2.2 (the previous version
dated back to February 2006). The work included the update of the hardware
libraries und the Wiki based documentation. The new
release supports now the filling of monitoring and configuration databases with
data of the DAQ process. In addition, the communication with the Lidar and the Calibration computer was improved.
·
Our
group was also actively working on the monitoring task (e.g. providing
PHP-scripts to display monitoring data and scripts). Details are reported by
Cyril.
R&D for Auger North and the HEAT proposal
·
First
new SLT board produced, test will be done in the coming weeks.
·
PCB
layout for new FLT still in progress.
·
Circuit
diagram for new AB (IPE version) is finished. The PCB layout design was
started.
WBS 2.1 SD (Ingo Allekote – Instituto Balseiro)
In the period February-March 2007 the following tasks have been
accomplished:
- Tanks received and inspected in Malargue: 0
- Detectors assembled: 8
- Detectors positioned: 28
- Detectors filled with water: 46
- E-kits installed: 88
Although we only count 8 tanks assembled, PMTs were
installed on many tanks that had been assembled before (and these have not been
counted again).
During February, water deployment occurred at the highest pace ever achieved,
but it came to a stop when we ran out of potted PMTs
to continue assembly.
As of March 31st, 2007:
- Total SD in the field: 1297
- Total SD with water: 1272
- Total SD with e-kit: 1215
The deployment in the
Tank CEIBO, which had a large erosion of the ground around it, needed
replacement to avoid a complete collapse of the tank. It was emptied and
replaced by the tank BOCA.
Vandalism to tanks was also registered. Tank Lucande
was perforated with a knife and was leaking badly. The tank has been retired
from the field and replaced. Although the tank might be repaired, the liner is
probably lost. Other detectors,
The surveying company re-measured with differential GPS a series of tanks whose
altitudes or positions were not accurately determined (mainly due to stakes
that were missing at installation times). This work has to be finished during
this month. Survey of the
Batteries are still a problem. The Moura batteries
that are in use for the SD have a very high failure rate. Prior to testing,
they need to be fully charged; testing takes a long time and large effort and
has to be performed on all batteries due to the high failure rate. A set of 8
intelligent battery chargers was purchased by
Two new technicians (Mauro Gajardo and Luciano de Rosa) have been trained and started to work on
SD assembly and deployment. Oscar Saez is now also
well trained for SD electronics deployment and maintenance.
Rotoplastyc in
Shipping has been further delayed pending transfer of the funds received from
the Brazilian Federal government through the research organization at the
R&D on rotomolding tanks with foam insulation
inside continues and three full size tanks have been made with foam insulation.
The three had foam thicknesses of 30-40 mm, 20-30 mm, and 10-15 mm. The last
tank had an unusually thin wall because the foam did not expand completely, so
this tank will be deployed as an ordinary Auger South tank. The foam thickness
in the other two tanks is much more interesting and they will be deployed as thermal
test tanks in Malargue as soon as shipping can be
arranged. These tanks still have some unevenness of the foam layer so
development work will continue. The interior of the 20-30 mm foam thickness
tank is shown in the figure. It is believed that slightly higher density foam
will be more stable during molding and produce a smoother, more uniform
interior. Rotoplastyc will make two test tanks with
the higher density foam and, if these are successful, they will be shipped to
WBS 2.2 Surface Detector Electronics
(Tiina Suomijarvi – IPN Orsay)
The total number of Ekits
assembled and tested in the SDE-Fabrica is 1484.
There are currently 180 Ekits ready for the field
deployment. Ekit
assembly will be completed in 2 months. 5252 PMTs
have been received from Photonis (total 5040+240
spares). More bases are currently being fabricated in
There are currently 1215 detectors with Ekits in the field
The deployment is now done by the SD group (maintenance is done by the SDE techniciens). A new SDE
tecnicien has been trained: Oscar Saes. Javier Alcaya, who has been
on leave due to his accident last November, will come back to work early May. A
second maintenance truck has been bought for the observatory.
The SDE maintenance is performed now since 18
months. Below is a graph showing the
maintenance rate per month (trips and tanks visited).

Figure : SDE maintenance
rate (by Walter Fulgione).
There are currently about 4 « black
tanks » per week. The efficiency in repairing them is above 97%. The table below shows the most common
failures.
|
replacing E-Kit (blown fuse) or fuse |
174 |
|
replacing Radio |
17 |
|
resetting Radio |
82 |
|
turn off/on |
9 |
|
other (batteries) |
23 (9) |
|
E-kit freeze or died because of PMT short |
18 |
Table : The most common
« black tank » failures.
There are currently about 2.7 new PMT failures per
week. These failures include connectors,
bases and HV problems. The efficiency of repairing is about 70%. Since all the PMTs
are currently needed for deployment, there is no PMT maintenance for the moment.
To increase the quality of the potting a clean room
for the PMT potting area has been made. About 350 PMTs
with increased potting quality has already been deployed to the field. However, no conclusions concerning the eventuel decrease of the PMT failure due to better
potting can be drawn for the moment.
PMTs failed in the field have
been studied in

Figure: “Square” response of
a PMT.
Gain jumps of
a few ADC channels correlated with curent jumps have been identified to be due to bad DCDC
converter. The
Several studies have been performed to confirm that
these PMT instabilities will not affect the data analysis. These instabilities
are of the order of a few ADC channels with characteristic time of about 10’. Due
to the calibration with background muons every
minute, these gain variations are compensated and do not affect the shower
reconstruction. The figure below
shows signal accuracy obtained by two
pairs of twin tanks. One of them, Dia-Noche, has an
unstable PMT. The signal accuracy obtained is similar for both cases.

Figure: Signal accuracy for
two twin tanks, one of them (Dia) having an unstable
PMT.
Similar studies show that there is also no effect to
the signal rise- and fall time and to the angular accuracy. A more detailed
report concerning the PMT instabilities and their effect to the data analysis
is currently under preparation.
WBS 4.0 Online Monitoring (Cyril Lachaud
– APC)
A workshop has been held between the 26th and 30th of March
in
I remind that you can watch the development on http://moni.auger.org.ar/dev or on the mirror http://apcpaox.in2p3.fr/AugerMonitoring/ (must be used when you're not in Malargüe).
A paper and poster dedicated to the Auger Monitoring systems will be presented at the next ICRC by Julian Rautenberg.
WBS 5.0 DPA/Offline- (Bruce Dawson, Markus Roth and Tom Paul)
A data production tag was made in March (v2r3p0-adst) for purposes of an ADST production run. A new full release is in preparation, but is awaiting resolution of some simulation and format conversion problems. The ADST writing modules are now distributed together with the
the Offline code.
In the detector description part of the framework, new capability for supporting station triplets (or other larger groups) has been added. An example program for generating station lists from the database has been prepared.
A database monitor has been set up which allows you to quickly check the last time data arrived in the master and mirror database. It's available it the offline wiki area:
https://www.auger.unam.mx/AugerWiki/NonEventDataBases
A prototype offline-python binding has been started, which has potential to help with interactive analysis and visualization.
In the SD reconstruction area, a new module for signal recovery has been prepared. The UCLA FADC pulse parameters module, for computing rise times, has been added to the repository.
The MC event generation module has been revised to provide more flexibility, including capability to choose a random station from the detector description and throw a shower in a hexagon centered on it. The fast and full geant4 simulations have been combined into
one, with a switch to choose custom photon tracking, reducing duplicated code.
To help with FD and hybrid simulations, a new FdUpTimeManager reads data from a root file (to be replaced by a database) giving dead time of eyes and telescopes, and dead time due
to the CDAS veto. In reconstruction, an updated FD pulse finder uses pixel FLT traces instead of telescope SLT data for pulse-preselection.
Radio Detection R&D – (Ad Van de Berg – KVI)
February and March. Near the BLS the installation for 2
stations by the group from OSU has been completed is running. For the third
station essential pieces were lacking. Locally generated 'radio' T3 requests
are being processed by the PC-DAQ system in BLS the container by observing a
close timing coincidence of T2 reports from the stations as well as making
random T3 requests when trigger rates are low for a background study. CDAS
generated 'real' T3 requests are also being processed with the local system
listening for requests to the surrounding tanks and the infill tank. For the
stations near the CLF radio-quiet units have been assembled and tested in
Malargüe Planetarium - “Planetario Malargüe”.
(Reported by Beatriz Garcia
and Carlos Hojvat)
The formal contract for the purchase of the equipment from SkyScan (USA) was signed recently. Construction of the delicate projection dome has commenced at the factory. Procurement of the remainder of the equipment including the special seats has started.
Discussions are being held related to the schedule for delivery and installation. As mentioned before, it is a digital planetarium to seat about 65 persons.
Some shows will be purchased to start operations, but there will be in house capability for programming.
The building to house the planetarium is near completion, the photographs show the actual auditorium were the projections will take place and the entrance area.
A team is being formed for the operation of the complex. There will be a general manager and personnel to take care of the whole facility that includes areas for other purposes.
The Planetario belongs and will be
operated by the City of
A “scientific team”, to look after the content of the shows, has been formed under Dr. Beatriz Garcia, UTN Mendoza and a collaborator in Auger. An advisory council, with persons operating other planetariums, has been formed and will hold it first meeting shortly.