Pierre Auger Project

Progress Report

 

 

Summary (photo album)

 

Three of the six telescopes at Los Morados recorded their first showers at the end of the March dark period and were in operation for the April dark period.  The remaining three telescopes at Los Morados are being commissioned.  All six need drum calibration.  Los Morados DAQ is running on a new code version that is still being debugged.  The Los Leones and Coihueco DAQ systems will be updated once the new code is commissioned.


There are 793 surface detector stations in the field.  Of these 764 have water and 697 electronics kits.  In spite of considerable effort the rate of detector assembly and water delivery remains well below that needed to finish the array in a timely way.  We are investigating the possibilities for obtaining more equipment and people.

 

The last of the communications equipment has been installed and commissioned at Loma Amarilla.  The tanks now being deployed in the north of the array can now be brought on line.  A number of antennas on tanks already in operation are being reoriented to Loma Amarilla.

 

Considerable instability remains in the data collection for a verity of reasons.  The sources of instability are mostly understood and solutions are being found.

 

We are also plagued by a decreasing data rate from the Auger campus to Lyon.  The bottle neck appears to be between Malargüe and Mendoza where the communications links are saturated.   Steps are being taken to negotiate a short term solution to this problem.  In the mean time we will start sending calibration data (and perhaps event data) by disk to Mendoza for upload to Lyon.

 

A number of events are being planned in association with the World Year of Physics are being planned.   Among these is the Auger Celebration to be held 9, 10 November.  The Auger Celebration marks approach to completion of the observatory and the presentation of the first physics results.

 

 

WBS 1.1 Fluorescence Detector ( Jonny Kleinfeller – Karlesruhe)

 

The status of the FD sites has not changed much since the last collaboration meeting.

We have three telescopes in Los Leones and in Coihueco equipped with corrector ring lenses, the lenses for Los Morados (promised for March 2005) have not yet arrived, but have been dispatched to Mendoza (C. Escobar).

At Los Morados are three telescopes in operation.
The new software has been installed on the eyepc. This software is identical to the software installed at Los Leones and Coihueco as far as operations is concerned, but adapted to the new LINUX operating system. Unfortunately most of the bugs have been transferred as well.

The a-calibration fibres have been installed.

Los Morados participates in the current shift with three telescopes (calibration and data taking).

Currently the remaining three cameras at Los Morados are being installed (mercedes, positioning, alignment).
I expect those telescopes to take data at least in one or two nights of the April dark period.

I have modified the fail safe-curtains in all buildings to increase reliability, seems to work.

The cloud camera for Los Morados is scheduled to be installed at the end of June.

 

 

WBS 1.2 FD digital electronics and readout systems (Matthias Kleifges – IPE)

 

Installation work on site:

 

We have installed the FE sub-racks and the MirrorPCs for telescopes # 4, # 5 and # 6 in the Los Morados building. These 3 telescopes took data in test mode (no T3 to CDAS) for the first time during the March shift at 17/18 March. Electronic gains and the HV values will be adjusted as part of the next drum calibration. Although the telescopes were not well adjusted, laser events from CLF as well as cosmic showers could clearly be identified.

As the adjustment of the cameras in bays 1 to 3 was not finished till the end of our stay, we only connected the MirrorPCs (MPC) and the FE sub-racks to the AC power from the SCS. Tests with the connected camera were not possible, but the MPCs boot procedure and the access to the FE crate was proofed to be working.

 

Other activities include following work:

·        A time calibration was performed for all telescopes in LL and Co (LM was unavailable at that time. The measurement uses the LCU to produce a LED pulse (semi-sinusoidal shape) and distribute it through fibre A to all telescopes in parallel. Taking into account cable delays and the light transit time in fiber A we derived stable calibration constants for both buildings (Co and LL) of about 315...320 ns for bays 2-5 and about 285...290 ns for bays 1 and 6 (due to longer cables from the GPS clock in these bays).

 

·        IPE has produced the electronic for a flashing calibrated LED light source which is fixed on a captive balloon. H. Klages and his crew performed first promising tests and record data with one telescope in LL. The analysis showed pulses in the virtual channel, but the normal channel saturated due to a factor 30 too high intensity. More measurements are planned with a modified setup.

 

·        Most of our time was devoted to find a bug in the DAQ readout system. For still unknown reasons the access to the front-end through the FireWire interface is sometimes inhibited, especially while performing calibration B and C (less frequent also calibration A). In this case, processes on the MPC stop and access to the hardware is no longer possible. The error diagnostic is very difficult as the problem occurs only intermittent on site and cann’t be reproduced in Karlsruhe. It also occurred with the new system in LM.
Information on the web claim an internal timing problem of the FireWire chip we have in use. In order to exclude the timing problem we have changed the firmware for the FireWire interface. The new version 4.7 may have reduced the frequency of occurrence of the problem, but didn’t let it disappear. We hope to get more information from the experience of the April shift.  

 

 

·        Adjacent telescopes in LM and Co are now interconnected by a twisted pair cable. Although the inter-telescope trigger is not yet supported by the DAQ, tests are now possible due to this cable.

 

DAQ and related software: (by H.J. Mathes)

 

Since the April shift the DAQ is identical for all FD buildings; the same DAQ code is running under Suse 9.1 in LM and under Suse 7.3 in LL and CO. The difference to the old DAQ versions is:

·        FDEventLib v2r6p1 implements the latest data format.

 

·        The DAQ controls the inputs of the GPS clock. Depending on the DAQ mode (calibration or shower measurement), the relevant inputs on the GPS clocks are enabled. The veto signal of the LIDAR is only enabled during shower measurements.

 

 

·        In order to avoid large T3 rates at CDAS several filters are implemented in the data path. 1.) LIDAR events are recognised from their GPS sub-second time and rejected. This however is only possible if the LIDAR is triggered by the FD GPS clock. We recommend applying a LIDAR hardware veto which makes this filter redundant.
2.) We apply a fixed software dead time after each T3 trigger send to CDAS. Events recorded during this software dead time are saved to disk without sending a T3 to CDAS. This filter is not yet enabled, as a similar rejection is implemented in CDAS software.

 

 

WBS 1.2 Fluorescence Detector Electronics (Daniel Camin – Milano)

 

FDE-Analogue

1) The development of the debugging system for the Head Electronics is progressing. The final version of the software (developed in Labview) is now released. This version comprises an optimized graphical user interface and some corrections of minor bugs. The design and fabrication of a printed circuit board for the PMT signal emulation circuit and the HE test fixture is underway. The system is able to perform 250 test ( two hours in continuous run) when the laptop is operated only in battery mode.

2) We have developed a procedure to determine the absolute pointing of all FD telescopes by looking to the signals left by stars, superimposed to the baseline over many months. The difference of the actual pointing compared to the specified values is, at most, 15 arc minutes in elevation and 13 arc minutes in azimuth. A modification in the elevation of telescope #3 in Cohiueco was "seen" by the programme as a difference of 0.13 deg in elevation. This program allows checking the long-term stability of the telescope's pointing.

3) The people of the Naples INFN Electronics Laboratory are strongly motivated to contribute to the construction of parts for the future upgrades. The Naples Electronics group counts with about 15 people with large experience in the design of boards that include Programmable Logic Devices. They are willing to participate in the construction and test of analogue boards as well. Their Lab is well equipped. We are in close contact with them and will interact
more closely as soon as the upgrades start to be defined. 

 

WBS 2.1 SD (Ingo Allekote – Instituto Balseiro)

 

In this period the SD crew at Malargue assembled 62 detectors, deployed 79 tanks, filled 73 with pure water and brought 87 new detectors into operation. As a result, as of March 31, 2005, a total of 765 SD were deployed in the field, of which 731 contained water and 686 had electronics installed.

Due to difficult terrain conditions in the area north of the Atuel River and to a series of problems
with the water transport trucks and front loader, the water deployment did not proceed as fast as expected.

Three tanks in the interior of the array, with extremely difficult access during the last two years, could finally be filled with water: Lisa, Maria-Maria and Castelao.

Progress has been made in the manufacture of the fourth water transport tank, Tk-12-DELTA. It
has been finished on April 5, 2005, and was delivered to Malargue on April 8th. All accessories are already available, so it is expected to enter in operation very soon.

On March 29, two days in advance of schedule, liner production was completed at the Liner Production Facility at UTN Mendoza. A total of 1501 liners were produced there, the quantity required to complete the array plus spares is now available. The liner facility will be dismantled and returned to the Technical University in Mendoza.

Brackets are being produced at Equipos y Proyectos in Argentina. A first test bracket was provided by this company and it was approved for mass production.

Rotopol completed the order of 200 Battery Boxes and pipes, which were all delivered to Malargüe.

Fermilab has submitted an order for resin for 309 tanks, to be divided between  Argentina and  Brazil based on funding availability for tanks at manufacturers in the two countries. Resin with UV-15 protection, to be used for the manufacture of battery box pipes, was also ordered from Icorene Brazil.

A battery testing and monitoring system is being implemented at the Observatory. It includes two levels of testing: one at the assembly building, under reception of the batteries from
the manufacturer, and another one which is done with data collected from batteries installed in the field. The manufacturer is supposed to deliver batteries in Malargue at 100% charge. In the first level, a fraction of the batteries is tested in the Assembly Building, by measuring the slope of the discharge curve under constant current. From the slope data it is possible to estimate the charge status and qualify the batteries as 'good', 'regular' or 'bad' for deployment.
The second level test is carried out with data acquired by the CDAS monitoring package. The data from each battery in the field is observed every day from 0AM to 4AM. During this
period the batteries should be smoothly discharging, providing electric power to the detector without sun light. Preliminary results of the off-line monitoring are shown at
http://www.cbpf.br/~lsd/Bat/Bat_1.htm.
In the near future, more information will be added to this web site, and an alarm system shared with Bugzilla and BigBrother will be set up, so that failures are detected and correcting
actions are timely planned.

 

WBS 2.2 Surface Detector Electronics (Tiina Suomijarvi – IPN Orsay)

 

The deployment of the Ekits goes smoothly. Special care should be taken with Black Widows who have invaded tanks. There are currently about 3-4 per tank.

 

The deployment was stop for a while due to the delay of the FE board shipment. The shipment arrived a few days ago and the SDE deployment will resume shortly.

 

Walter Fulgione will be on site in May and a major campaign of PMT maintenance will take place.

 

About 60 % of the PMTs  have now been received in Malargue. The rate will continue 144 per month.

The new master order has been sent to Photonis for the rest of the production.

 

 

Figure 1. PMT statistics by Federico Suares.

 

If the cable failures are ignored (they can be repaired on site), the PMT failure rate on the field is about 3%. The majority of problems are early on bathtub curve (infant mortality). Two PMTs failed after >1.5yrs in the field (they are to be recovered and tested). Some problems have not been fixed in a timely fashion, a couple of the problems have been “fixed” multiple times. A PMT batch with temperature problems to be sent back to France for further studies.

 

The Ekit failures on the field are large, about 5% for the UBs. The distribution of the failures among different components is shown below.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Figure 2. Ekit failures.

 

Most of the UB failures are due to blown fuses. As a corrective action, the fuse size has been increased and the failures are being carefully monitored. The “not detected” failures are mostly failures to obtain a radio connection. This is probably due to some installation problems and has been fixed with new procedures.

 

The figure below shows the trigger uniformity.

 

 

Figure 3. The trigger uniformity.

 

The tanks that have been recently installed have higher ToT rate than the older ones. A stabilization time of a few months is required before the trigger rate falls into the normal rate of about one Hz.

 

 

 

Figure 4. Stabilization of the ToT trigger rate.

 

The muon spectra are carefully monitored. The following figures show the results of the monitoring.

 

 

 

Figure 5. the RMS over mean values for PMTs for different time periods.

 

Figure 6. The RMS over mean values for the areas of the muon signals.

An anomaly is observed for the period of January to February. The table below shows the results of the monitoring.

 

 

 

The high dispersion of the VEM area values during the period of January-Frbruary still needs to be understood.

 

The good news from the UCLA long term monitoring are:

          ~90% of tanks have smooth behavior:

        <10% loss in Area/Peak ratio at the beginning.

        Characteristic time is ~ ¼ year.

        ~1% of seasonal variation, strictly correlated to annual temperature change.

          These tanks will survive for 20 years!

        Initial quality loss happens within ¼ year.

          Water quality or

          Tyvek reflectivity

        Then it goes into extremely stable condition.

 

 

Concerning the fabrication of SDE components there are also some good news:

          KVI (Netherlands) will fabricate 800 TPCBs

          Wuppertal will probably be able to fund and fabricate the remaining FE boards. 

The Cyclone boards have been successfully tested in Malargue  and a critical design review will take place during the analysis meeting in Orsay (June 6-10).

 

WBS 3.0 Comms (Paul Clark – Leeds)

 

We passed a number of major milestones in the Comms task recently

 

19th March - Completion of the last Communications tower

 

March 19th saw the installation of the last piece of Comms hardware (a 1.2m microwave dish) on the last tower in the backbone system. All 5 towers are now fully operational with 28 base-station sectors available for the surface detector array (capable of supporting 1680 surface detectors) and a 2Mbps dedicated link available for each FD eye building.

 

April 6th – last radio leaves the test chamber – final hardware shipment imminent

 

Last week the last radio left the test chamber at Leeds and we are packing the last shipment of radio hardware now. Once it arrives in Malargue it will make a total of around 1760 Subscriber and Base-station radios supplied to the project, including sufficient spares to last the planned 20 year lifetime of the Observatory.

 

Comms procurement completed

 

All the required components for the SD Comms system for the full array have been purchased and the vast majority of equipment is actually in Malargue now. The final shipments will arrive at the site over the next couple of months.

 

Surface Detector Antenna Team

 

Jorge’s team continue their good work for the Comms task in Malargue;

 

 At the moment they have several programmes of work underway

 

1.      Antenna Kit Preparation – the total number of kits made is now 915 (with the hope of reaching 1000 in May)

2.      Antenna Kit Deployment – (performed by the water teams and managed by Jorge) – 740 installed in total

 

49 Kits were mounted during January

 

38 during February

 

39 during March

 

3.      Antenna Heatshrink ultraviolet protection programme – this campaign aims to make sure that no heatshrink on the antenna system is directly exposed to the sun. This has required retro-fitting protective tape to a total of 275 kits – current progress, to date 116 kits have been protected.

 

4.      Antenna Re-orientation programme – with all comms towers now complete and the array filling up, it is necessary to re-orient ~100 antennas to their final tower – these antennas were pointed to an interim tower during construction when the correct tower was unavailable. A plan is in place and future reports will provide details of progress made (how many done and to-do).

 

WBS 4.0 Central Data Acquisition System - (Antoine Letessier-Selvon – LPNHE)

 

The following are the current CDAS problems:

 

1] NFS server (network file system service) / disk space crisis



2] NTP server (network time protocol service). Broken Antenna



3] Ik/Cm (Information kernel, Communication manager) saturation



4] Fd shifts (Trigger problems)



5] Network access to Lyon


And here are their present status


1] New RAID array hardware bought and installed. Compatibility problem with NFS solved.
Data storage partition is now 551GBytes less than 40% used.

2] Problem forwarded to the on site maintenance (Ruben). No solution yet. Need to buy a new antenna.

3] Hopefully solved. This ultimate part of the code that was not written by CDAS team members has been entirely recoded by Patrick and Xavier.


4] Several actions taken on the Fd side. On CDAS side a new veto with better characteristics was
implemented (see Xavier message as above). Also some of the comms bug we had were solved.

5] Link is desperately poor (average 300kbits instead of 1000) but amount of data sent to Lyon through the link has been drastically reduced. See e-mail on how to transfer CLF data using DVD and UTN in Mendoza. Meanwhile there is a strong effort from our European colleagues to upgrade our link to Mendoza.

 

WBS 5.0 DPA/Offline- (Bruce Dawson, Markus Roth and Tom Paul)

 

During the past two months, the offline development team has focused on addressing the issues raised at the PRR held last November, especially in the areas of code stability, release frequency, ease of installation and database filling.

A new set of release procedures has been adopted, as described in detail at https://www.auger.unam.mx/AugerWiki/ReleasePolicy. Briefly, releases will henceforth be categorized as either "beta" or "production", with beta releases occurring at regular intervals (generally bimonthly) and production releases being generated as needed.  Specific milestones
are attached to each beta release and tracked via the offline bugzilla system.  This helps the development team prioritize its workload, plan specific release dates, and assess progress.  The production releases are meant to be prepared in close consultation with relevant analysis
coordinators, and will be split off onto separate CVS branches. Keeping them separate from the main development trunk insulates production code from day-to-day work of the development team and thus ensures stability of the code used for actual physics analysis. A first implementation of these new procedures has been carried through, with beta release 1_1 cut in March and a first SD simulation production release prepared in February in close collaboration with Maximo Ave and the SD simulation group. A new release policy for offline databases has also been implemented, and is documented at https://www.auger.unam.mx/AugerWiki/ReleasePolicy.

To help ease installation of the code, a new script has been prepared which builds all the required external packages, including Geant4, as well as the offline code itself.  The installation instructions have also been substantially revised, and are now split into a short section for beginners and a detailed section for advanced users who may wish to customize their installation or build directly from the CVS repository.  Scattered web pages have been consolidated into one wiki-based Offline portal.

The offline databases have undergone some further revisions, and are being populated with data.   The molecular databases now contain Leones and CLF weather station data, 92 radios on  campaigns, as well as US-StdA and Malargue monthly averages.  The Leones and Coihueco drum calibrations have been written into the FD database, and the SD monitoring database has been filling automatically since January.  The automatic master database updating and backup scheme has been running for about a month.

Development of modules has also progressed well. Particularly important, the full hybrid simulation chain is now operational.  The CDAS team has provided modules which allow one to directly invoke the event selection and calibration codes of the CDAS package.  Support for CDAS v.4 has also been prepared and will be available in the next beta release. The Offline Modules area now contains 20 contributed module directories.

 

WBS 8.0 Education and Outreach (Greg Snow – University of Nebraska)

 

Construction begins for the new James Cronin School

A groundbreaking ceremony for the new James Cronin School of Communication, Art, and Design was held in Malargüe on February 7, 2005. The 822 square meter facility is foreseen to be completed in about 6 months and will replace the present Escuela 4-190 that has an enrollment of approximately 200 secondary students. The new building is made possible, in part, by a generous donation from the Grainger Foundation in the United States. It will be located a few blocks from the present school on a site donated by the city of Malargüe. Two photos in the gallery of this report, taken in March, show that the construction of the new building is underway.

 

World Year of Physics events in Malargüe

A number of events in Malargüe and Mendoza Province will be held in association with the 2005 World Year of Physics (WYP2005) during the upcoming months. The inaugural event occurred during the March collaboration meeting when Dr. Raúl Grigera, a biophysicist and President of the Physical Society of Argentina, presented a talk entitled

“The World Year of Physics, an Event for Everyone” in the Convention Center on March 15. The city of Malargüe presented a certificate to Dr. Grigera after his presentation, as shown in the photo gallery of this report. Auger collaborators also mounted a WYP2005 display in the entrance of the Convention Center, and photos of the display appear in the gallery.

 

Preparations for upcoming events

During the March collaboration meeting, planning and preparations began in earnest for two major events in November. The first is the Auger Observatory Celebration, November 10-11, to which many dignitaries, representatives from supporting agencies and institutions, special guests, and the press will be invited. The two-day event will include an official ceremony, a number of talks about the Observatory, and tours of the site. The second event is an Auger-sponsored science fair for Mendoza Province students and teachers that will take place in the Assembly Building on November 11-12, just after the Celebration. Five Malargüe teachers serve as the local organizing committee. Proposals for projects to be displayed will be accepted through the end of June, and sixty projects will be selected to participate in the fair. A team of Auger collaborators will serve as judges, and prizes will be awarded to the top displays in several age and topic categories.

 

 

WBS 9.0 Observatory Operations – (Julio Rodriquez Martino - INFN)

 

The FD trigger problems continued during February due to a large number of thunderstorms seen in the vicinity of the site. The situation was far more stable in March. As a temporary solution, a trigger veto was implemented from the CDAS side, to avoid that the high rate coming
from the FD during these particular data taking conditions crashes the system. The FD T3 algorithm is being improved. I have already programmed a new version that is being tested off-line and that will also be evaluated using simulations, to study its impact on the detection efficiency.

A program to analyses the FD run data was written. It tests the quality of the events using different parameters. The description of the program and the analysis method will be part of a GAP note, also proposed as an ICRC poster. Results from this program will soon be displayed in the FD web page, as a way of monitoring the data quality.

Transfer of LIDAR and CLF files to Lyon was suspended from the end of the March FD shift, as a way of saving internet bandwidth. The data is now kept in the calibration server (calib.auger.org.ar) and should be analyzed there.