Pierre Auger Project
Progress Report
Summary (photo
album)
The important news this month is that we have obtained an agreement for access to Felix/Sat land for deployment of surface detector stations. Over the next few weeks this large hole in the array immediately in front of the Coihueco fluorescence building will be closed up. Survey for tank positions is underway. The staff has made excellent progress installing and filling detector tanks in the eastern part of the array including difficult areas that are normally too wet to access.
The last of the tanks are arriving from
Two of the three foundations for the HEAT telescope
enclosures have been finished. In early
February the installation of the ground plates and tilting mechanics will
start. Electronic components for the
Heat telescopes are being completed and will be shipped to the site from
The design for the Auger North detector continues to evolve
in preparation for submission of funding proposals toward the end of 2008. A symposium entitled International Astroparticle Physics Symposium is being planned for
6-8 May in Golden,
WBS 1.1.3 Fluorescence Detector Calibration (Jeff Brack –
Recent progress on FD calibration has focused on the relative calibration data analysis with the goal of filling the offline database with nightly calibration constants. The main data analysis effort is now centered in Catania. All calibration data from the calA fiber for 2007 have now been analyzed. The Prague group is now working on analysis of calB/C data. Work continues on defining early epochs for the calibration database (CSU and Malargue), and on construction of software machinery for auto loading the nightly database once it is ready (UNM). A model of FD PMT response as a function of time has been developed (Rome2) and has recently been improved to include events from the monitoring database such as shutterdoors opening/closing, HV on/off and the effects of cloud cover on night sky background. With adjustment of parameters, the model can track the observed PMT degradation over time. Plans for moving the Malargue FD calibration lab into the AB are still in flux. The small AB dark room will be used for lab space. One configuration being considered for drum calibration is to build a permanent dark room inside the AB hall, covering nearly half the hall floor.
WBS 1.2 Fluorescence Detector Electronics
digital electronics and readout systems (Matthias Kleifges – FZK-IPE)
DAQ software (H.J. Mathes, M. Sutter)
· Currently a lot of time is spent for
tests and reorganisation of the DAQ software. Unfortunately, automatic file
transfer from FD computers to
· Nevertheless the FD-DAQ version
3.3.2-4 was installed for the (current) February 08 shift. This new version
allows setting the parameters of the TLT algorithm via ini-files and logs the
settings in the monitoring database. It is accompanied by the new FDEventLib version
v3r5; version v3r6 is under preparation together with the corresponding IoFD
v3r6 (holding routines to read/write events).
· A new GUI to operate the DAQ is
under development by M. Sutter as part of the Auger ACCESS project. Interfaces
to the DAQ software have been defined and the new GUI will allow steering of
all buildings simulateously.
Other software (A.
Kopmann)
· The recording of statistical data
(variances, pedestal, hitrate, and threshold) with the command ‘bgrecord’ was
revised and debugged. The operation is now more stable and the writing of
pedestal values in the monitoring database is now correct (before a constant
value of 150 was written).
· There is now a library of LabView
functions available to access the Pbus class. This eases the programming of
software for hardware tests using LabView.
R&D for HEAT (and Auger North)
·
The
component to steer the shutter, the fail-safe curtain and other sensors/actors
of one telescope have been consolidated for the first time in a single control
box (see photo). The new design by N. Barenthien saves a considerable amount of
material and thus reduces production costs assembling time. The boxes and other
mechanical parts for HEAT will be shipped by sea cargo from
·
The
development and production of components for HEAT electronics proceeded. The
current status is:
-
One
SLT of the final design (version 4.1) is assembled and completely tested, i.e.
the interfaces between the FPGA and all periphery (memories, backplane buses,
PCI, PrPMC module) are verified to work. As soon as time permits the IPE
fabrication center will assemble 7 more units, which will be used by the KATRIN
and the USCT project, too.
-
10
PrPMC computers PSL09 have been procured and tested sucessfully.
-
A
revised FLT circuit diagram (version 4.1) is completed, but the changes have
not yet been incorporated into a new FLT PCB layout. In parallel to the PCB
work the components are currently procured (main parts have already been
delivered) and the firmware is developed.
-
F.
Guarino (INFN Napoli) and his colleagues have finalized the design of the HEAT
analog board. Four prototype boards with two different bandwidth (3 and 6 MHz)
will be available within the first week of February to measure the performance
(linearity, bandwidth, cross talk and functionality). The group has also
developed a test board which allows to set the gain for normal and virtual
channels and to inject input signals to predifined channels. Our goal is to
carry out an integration test of AB and FLT beginning of March in
WBS 2.1 SD (Ingo Allekote – CNEA)
Delivery of tanks from
Rotoplastyc in
delivered to Malargue before the holidays. Unfortunately, the Brazilian
trucking company did not get the highway permits for any deliveries after the
holidays and failed to deliver any
more tanks after the original 54 through the end of January. As a result,
assembly and deployment of surface detectors stopped when the existing supply
of tanks ran out. The first delivery in 2008 is expected to arrive in Malargue
in the second week of February. (All the tanks have been made. The
problems have simply been with the delivery.)
Development of foam-insulated tanks for possible use in Auger North has been
slow at Rotoplastyc. It is believed that the variable quality of the foaming
resin available in
been part of the problem with the inconsistent results produced by the tank
development work. A shipment of foaming resin from A. Schulman Inc., the
company that produced the high quality
resin used for nearly all of the SD tanks, was sent to Rotoplastyc and tests
with the small mold and the Schulman foaming resin have begun. An even smaller
mold, enabling tests to be made with the use of even less resin per test, has
been built.
Development of foam-insulated tanks by the Rotoplas company in
the three had good results, and the third (and largest at 155 cm) test was not
successful. They are continuing their development work.
A company in the
The basic facts for the period Dec 2007 - Jan 2008:
Tanks arrived: 18
Detectors assembled: 38
Detectors deployed: 38
Detectors filled: 55
E-kits installed: 17
As of December 31, 2007, there were:
detectors in the field: 1589
detectors with water: 1540
detectors with electronics: 1475 (according to Little Brother)
As of January 31st, 2008, there were:
detectors in the field: 1597
detectors with water: 1570
detectors with electronics: 1481 (according to Little Brother)
Batteries are a continuing problem. Although a batch of 100 additional
batteries have been purchased in december,these were not delivered until the
beginning of February 2008, thus
delaying the electronics deployment and the entering operation of many tanks in
the northeastern part of the array. Recently received shipments still show a
high rate of batteries failing to pass the initial quality tests.
Deployment of the detector tanks that were received at the end of 2007
continued both in the land of the Italians as well as in two portions of land
south of it, next to the
Although it costed a huge effort to reach this difficult area, most of the
tanks were filled with water.
Access to the land owned by Felix and rented by Sat has finally been granted to
Auger! This is basically the last portion of large land where an agreement with
landowners was pending
resolution. Access to Felix/sat will allow to fill the last big hole in the
array. Tanks are expected to be deployed in this area starting in February,
soon after the next tank shipment arrives.
WBS 3.0 Comms (Jorge Abraham
– UTN)
- AntennaKits mounted: 1569. (See Image: AntennaKitsDply.JPG. Green and Blue SD have AntennaKits Installed). - AntennaKits made: 1660. We finish this part of Task !!!!! Reported in my last Bi monthly report. - I make a control periodic of the SD Signal quality.(See Image:SU-Signal.JPG).About bad links, We will change some AntennaKits for High-Gain AntennaKit to solve the problems. May be during the first six month from 2008.
WBS 5.0 DPA/Offline- (Bruce Dawson, Markus Roth and Tom Paul)
Extensive tests are currently being performed on the new SdCalibrator module. The next release is on hold until these are finalized. New external package distribution kits are being prepared for the release. A prototype CMake build system is in ongoing development. This system should allow for easier maintenance of the build for the growing Offline system. The buildfarm has been substantially upgraded, and now includes (among other features) a build on mac OSX.
WBS 9.0 Observatory Operations – (Julio
Rodriquez Martino - INFN)
The FD data taking continued
without major problems. Only weather, power cuts and minor failures prevented
normal operation in very few occasions.
Relative calibration analysis is being performed in the calib PC in Malargüe in
order to reduce transfer delays and impact on the bandwidth of the link.
Further analysis will be performed
locally one the system shows is tested.
The monitoring part of the FD is getting more robust as more shifters are using
it. The diagnosis of the calibration runs will be performed directly in the
monitoring system to let the shifters
troubleshoot the system.
Primo installed a light sensor in bay 5 in Los Leones, this is a first
prototype but future improvements could allow us to know when it's time to open
the shutters again if the cameras have seen too much light.
WBS 9.0 Observatory Operations cont. – (Ricardo Sato – Southern Observatory)
In this
particular period of the year, the problems are mainly related with storms. The
main problem generated by storms is power cut mainly in the Los Leone and Los
Morados buildings.
On Dec. 26th, 2007 for example, we lost about half of all array because a power
cut happened two days before. This particular problem has been fixed only on
Jan 2nd, 2008. It happened because the problem was not just a blown fuse, but
some problem related with power line
Los Leones - Los Morados.
Beside the power cut problem, there is another one which looks to be related
with one GPS in one uLSx which controls communication of BSUs 11, 12 and 13. It
make the stations close to the Los Leones tower not connect just after the
power come back and is necessary to someone goes
to Los Leones building to fix the problem. This particular problem happened in
the last three disconnections happened due to power cuts at Los Leones
building.
Radio
Detection R&D – (Ad Van de Berg – KVI)
· The radio R&D setup near the CLF system has been used to identify for the first time self-triggered events. It was discovered that for the GPS used by the UB the nanosecond time had not been correct. This error has been fixed and the old data set has been reanalyzed. In the time period from mid-July to mid-November 4 events have been detected in coincidence between SD and 1 antenna; 1 event in coincidence between SD and 2 antennas.
HEAT enhancement -Hans Klages (FZK)
The HEAT site
preparation is making good progress. In January, two of the three foundations
for the telescope enclosures (pits) have been finished.
In pit no.3 the concrete will be poured in the first days of February. The site
preparation work is ahead of schedule by about one week.
At the time of the collaboration meeting the installation of the ground plates and
tilting mechanics will commence.
Visitors are welcome - helpers even more.
AMIGA - Alberto
Etchegoyen
AMIGA is ordering the first full electronics prototype
boards and the FPGA programming is fairly advanced. Forty 64-pixel PMTs
with resistor chains and HV supplies have been ordered. At the
beginning of February, the new AMIGA WiFi system will be installed to
the BATATA three tanks with a Coihueco access point. It will be a
bidirectional system with the Central Station.