Pierre Auger Project

Progress Report

 

 

Summary (photo album)

 

The construction of the Observatory is humming.  The installation of the telescopes at Los Morados is proceeding very smoothly helped by the newly completed power line.  As of this writing (17 February) the mirrors are all installed and mounting of the cameras has begun.  Commissioning will begin in April.

 

We now have a presence at the at the Loma Amarilla fluorescence site.   The communications tower was completed and the antennas rigged in December.   Unfortunately legal problems associated with the ownership of the land have delayed the start of construction of the Loma Amarilla building. 

 

There are now 715 tanks in the field, 683 of which have water and 652 have electronics.  Good weather has speeded deployment although the distances and travel times from the campus to the detector sites continue to increase.

 

Plans are being made for the grand inauguration of the Auger Observatory on 10-11 November, the week before the collaboration meeting.  In the morning of the first day there will be some talks on the Auger science and on the construction of the Observatory for a general audience.  In the afternoon the inauguration ceremony will take place followed by a dinner.  On the second day we will provide our guests with guided tours.

 

Other news:  The construction of the new building for the James Cronin school has begun.  The school is funded by a grant secured by Jim from the Granger Foundation of Chicago.  The new building will provide the first permanent home for the school.

 

 

WBS 1.1 Fluorescence Detector (Jonny KleinfellerKarlesruhe)

 

Los Morados


At last, the air conditioning is in operation, just in time to the fine tuning of the mirror alignment in Los Morados.

Filters, corrector ring frames and safety curtains are mounted. As of today, Monday February 14, 2005, the mirrors of telescopes 10, 11, and 12 are mounted, the other telescopes will have their mirrors mounted by Wednesday of this week.

LAN and the slow control system are completed, all sensors are installed, tested, and fully operational. Shutters and curtains are integrated into the slow control system, the interlock are in operation, except for the HV / LV system, which is not yet in place.
Los Morados is ready for the installation of the cameras. The cameras are expected to arrive at Los Morados this week.

There is no DAQ installed on the EyePC of Los Morados. The EyePC at Los Morados is a new system running with a newer version of SUSE, which requires major changes of the existing DAQ software.
The DAQ is scheduled to be implemented in March. The EyePCs at Los Leones and Coihueco are going to be replaced by the new type after the DAQ has installed successfully at Los Morados. The new EyePCs are already mounted and configured for the LAN at these buildings, but currently disconnected.

HV/LV cabling for the cameras is 50% ready, completion in February.
Installation of electronics is scheduled for the end of February.

Coihueco

 
The safety curtains have been replaced by a new design, the major change is the drive mechanism, a cam belt, instead of a rope. This should overcome the frequent misalignment of the curtains.
The missing four corrector ring frames have been mounted.
Coihueco is completed to the point that only the corrector ring lenses are missing.

Los Leones

 
The service cranes have been installed.
As in Coihueco, the safety curtains have been replaced by the new design.

 

 

WBS 1.1 Fluorescence Detector Calibration (John Matthews – University of New Mexico)

 

The status is that the initial installation of the new Morados APF is complete.  Only the wide wavelength light source is installed at this time.  The control computer is in the calibration room of the Morados FD building and runs the Morados APF via a radio link.  All components

have been tested and work well.   Routine operation of this source awaits completion of the Morados telescopes as the FD telescopes are needed to measure the light scattered from the APF light beam(s).

 

The status of the Coihueco APF is that 3 sources are installed:

one wide wavelength and 2 narrow (10nm) wavelength beams centered on 334nm and 390nm.  At this time only the wide wavelength source is run.  It fires a set number of light pulses, across the field of view of the Coihueco FD, every hour during FD data taking.

 

 

WBS 1.2 FD digital electronics and readout systems (Matthias Kleifges – IPE)

 

Installation work on site: (by N. Kunka and N. Barenthien)

 

The installation of telescopes in the Los Morados building is progressing within the schedule presented at the November Malargüe meeting. Main installation items from the FD digital electronics group are:

·        The building is now equipped with complete LAN infrastructure. This includes the Mirror LAN (the LAN connecting the Mirror PCs with the EyePC) and the Eye LAN (connecting the EyePC with all other subsystems and the telecommunication).  WLAN access is possible and all necessary services (like DNS, time server, etc.) are configured. The UPS of the EyePC is in place and will provide monitor information on times of power breakdowns (if they are long enough).

·        In all 3 buildings (Los Leones, Coihueco, Los Morados) new 19” rack mounted RAID computers are built up. They will replace shortly the current EyePCs. Due to the raid disk the system reliability is very much improved. However, they will operate only with newer Linux releases (we use the German SuSE 9.1 version). The Linux system has been modified for the automatic boot procedure of the MirrorPCs and its file system. The boot process and system functions have been tested with all MirrorPCs (in LL, Co, LM).

·        An additional raid system was installed in Karlsruhe. It is currently used as platform for the conversion of all user software to the new Linux.

·        The SCS system is installed in LM in all 6 bays. It includes among other things the shutter control, the fail-safe- curtain steering, relays for the power control of FE sub-rack and MirrorPC, light sensors, and the interface to the High Voltage system. Tests of the systems with the newest SCS software are in progress.

·        The BIOS settings of the MirrorPCs are stored in CMOS memory which is buffered by a small battery cell. In the past we had frequently problems with non-booting MirrorPCs caused by lost BIOS settings. In close communication with the PC manufacturer we got an Auger-specific BIOS which holds our configuration as the default one. Thus even without the battery backup the PC starts the boot process with the needed settings.

 

DAQ and related software: (by H.J. Mathes)

 

The search for bugs and the implementation of new features in the DAQ is continuing. First the DAQ in the current version but for the new Linux System will be installed in LM, but soon a new DAQ release will cure following bugs:

·        Memory leaks in the Eye Run Control GUI will no longer crash the DAQ in longer runs. In addition, the robustness against communication failures of this software part is increased.

·        The scheme for registering of CORBA based programs at the (3rd party) CORBA Naming Service (NSD) is changed to avoid continuous memory consumption by the NSD leading to unpredictable system crashes after some weeks.

·        The data flow inside the FD event builder will be changed. In future “minimum bias” events - i.e. a fixed percentage of events rejected by the TLT but recorded for investigations of the trigger performance – will bypass the T3 algorithm. The same is true for events from external light sources (CLF, APF) as these event types are then already tagged by the Mirror DAQ. This results in a relief of the TLT and T3 data throughput.

·        A new FDEventLib will improve the compatibility with 64-bit and PPC platforms and implement minor extensions and corrections towards proper C++ coding.

 

Other activities in IPE:

·        The program for hardware tests of the FE sub-rack is now available for Linux. Online help functions are integrated. The hardware access is either from the EyePC via the MirrorPCs possible or from a service laptop.

·        A service laptop (dual-boot Windows and Linux) was installed with necessary program for use by Primo Vitale. 

·        H. Klages has proposed to check the FD calibration by means of a captive balloon equipped with a flashing calibrated LED light source. We have designed the flying LED flasher which will be operated using a commercial radio control and interfaced to a GPS receiver for determination of its position. Components for 3 devices are procured. First tests are planned in March 05.

·        We have started activities to measure cosmic ray showers with radio detectors. The design of a logarithmic, periodic dipole antenna was finished and successfully tested in Karlsruhe. The antenna consists of 2 perpendicular arms (crossed design) to allow measuring both polarisations. Since a few weeks we have 3 antennas in an equilateral triangle configuration mounted on our roof. They are equipped with low noise preamplifiers and analog filters. For signal recording and triggering we use a commercial VME system, but the development of “digital radios” for that purpose are planned. The measured data is offline compared with data from the close-by KASCADE experiment to find out how a self-triggering of radio detectors is possible.

 

WBS 1.2 Fluorescence Detector Electronics (Daniel Camin – Milano)

 

1) Debugging system for the HE + PMT assembly the development of the HE debugging system is now completed. The system is fully portable, the software (implemented using Lab view) is installed in a laptop computer equipped with a PCMCIADAQ Card (National Instruments 6062E, 500ksamples/sec). The power required by the Head Electronics under test and the analogue part (PMT signal emulator and the differential receiver) is delivered by the laptop battery, via the USB connector (5 Volts, 500 mA).The different voltage is required by the unit under test are obtained by means of a DC-DC converter and linear regulators. In the same computer there is the data-base server in which the parameter for each HE unit are stored. The data-base contains the parameters measured during the production phase at the manufacturer plant, Elbau/Intratec, in Berlin. The system is able to perform a database query and makes a comparison between the measured HE parameter and the production parameter. The production of a printed circuit board and the HE test fixture is underway.

 

 

 

 

2) Determining the pointing of the FD telescopes. We have calculated the absolute pointing of the FD telescopes from the analysis of sky background data acquired during regular data taking periods. The method we used (see GAP-2005-008) is based on the knowledge of bright stars coordinates that provide a reliable and stable coordinate system. It can be used to check the absolute pointing of the telescopes as well as its long-term stability during the whole life of the project. We have analyzed background data taken from January to October 2004 to determine the absolute pointing of the 12 telescopes installed both in Los Leones and Coihueco. Our method is based on the determination of the mean-time of the variance signal left by a star traversing a PMT's photocathode which is compared with the mean-time obtained by simulating the track of that star on the same pixel.

 

 

WBS 2.1 SD Site (Ingo Allekote – Instituto Balseiro)

 

 In the two-month period ending January 31, the SD crew at Malargue assembled 56 detectors, deployed 67, filled 87 with pure water and brought 55 new detectors into operation. As a result, as of January 31, 2005, 686 SD were out in the field, of which 659 contained water and 602 were in operation. Tanks have been deployed in several new areas, including along Route 40 near Coihueco.

The fourth water transport tank, Tk-12-DELTA, is still under construction, as the provider has reported some delay in the manufacturing process.

The stainless steel tanks for water transport suffered a lot under the vibrations due to the uneven roads to Morados and needed to be repaired a couple of times in San Rafael.

During January, a large road grader was borrowed from CNEA San Rafael to improve the roads to Morados and to open new tracks to the central part of the array North of the Atuel River.

Manufacture of 134 tanks in Argentina, funded by the University of La Plata with a grant from the Antorchas Foundation, was completed and the tanks delivered to Malargüe. In addition, the manufacture of eight tanks was funded by Mexican universities: two by UNAM and six by Puebla. (Resin for all these tanks was funded by Fermilab.)
All the resin that was in Argentina, stored and distributed through Tandar, has now been used. Funding is not yet available to buy more resin but efforts are continuing to obtain that funding and resume tank production in Argentina in a few months.

Resin for 209 tanks was purchased by Fermilab and shipped to Brazil for manufacture into tanks. Funding for the manufacture and shipping of these tanks has been secured from both the Sao Paulo funding agency FAPESP and from the Ministry of Science of the Federal Government. The resin has arrived in Brazil and will be available for tank production as soon as the last formalities in Customs are complete. A third transport trailer has been prepared and tanks should be delivered to Malargüe at the rate of about 24 per month.

Battery boxes are being manufactured at Rotopol. The battery boxes are of suitable quality and production will continue. The UV-15 resin purchased as a test, with extra additives to increase the ultraviolet aging resistance of the part of the battery box that is in direct sunlight, has molded well. It is being used up rapidly and more battery boxes will be required than can be made. Purchase of additional UV-15 resin is being arranged by Fermilab. In the meantime, some of the UV-8 resin at Tandar will be modified with additives at Rotopol in an effort to provide the same UV-15 ultraviolet resistance. No delay in production of battery boxes needed for deployment is anticipated. The battery box production is managed by Tandar and Bariloche.

There was a problem with some of the solar panel brackets when they were delivered to Malargüe: The holes for mounting the panels were located properly for an early version of the Isofoton solar panels. The assembly crew in Malargüe was able to provide a temporary procedure to assemble the brackets by relocating some holes. The manufacturing problem was traced to using the original drawings for the brackets. When modified drawings were used later, they were never officially revised and installed in the CERN EDMS database that Auger uses for all official drawings. The revisions have been made to the drawings and the revised drawings are now in the EDMS database. Production of solar panel brackets is proceeding smoothly, managed by Tandar and Bariloche.

A group of solar power regulators failed during this period in the field. The failure was due to a manufacturing fault and was confined to regulators in a narrow serial number range. Nearly all of the forty or so regulators involved have been recovered from the field and a sample of eight has been sent to the manufacturer for review and replacement.

A shipment of 1024 more solar panels arrived, provided by Spain. These panels should be sufficient for assembly and deployment beyond next September. Solar panels for the
remainder of the Array plus spares have been ordered by Spain and are expected well before the present stock is used up.

Two developmental fiberglass tanks were delivered to Malargüe and inspected. There were a few manufacturing errors that can be corrected in any future procurements. These tanks were assembled into surface detectors and are expected to be deployed soon



WBS 2.2. Surface Detector Electronics (Tiina Suomijarvi – IPN Orsay)

 
 

Status of the SDE-Fabrica

 

The FE and TPCB boards are the most critical items due to their small batch sizes (typically 100). Currently 100 TPCBs are in transit and the assembly and testing of E-kits which was stopped in December due to the lack of these boards, should resume next week. The small batch sizes of these boards are due to the lack of funding.

 

The radio test bench which was not operating properly is now working and allows to diagnostic radio field failures. A few failures of the GPS receivers have been detected and a test bench for the GPS cards will be installed in the SDE-Fabrica.

 

There have been some problems in the UB shipments. Some of the boxes are damaged when arriving to Malargue. However, no mechanical damage on the UBs was observed in the last shipment.

 


Status of the PMT-house activities

 

There are currently PMTs arriving in batches of 36 corresponding to two different orders: the order from the collaboration and the order from Italy. The table below gives the latest status of the PMT shipments (order of the collaboration by Penn State).

 

 

In addition to this order by Penn State for the collaboration, Italy has ordered 684 (total) PMTs and Chech Republic 290. The total number of PMTs currently ordered is 3499 and the total number of PMTs delivered is 2955. It is now urgent to place a new master order to Photonis for the remaining part of the PMTs. France is currently transferring funds to the CERN account for 1000 PMTs.

 

The failure rate in the PMT tests is low. The most frequent failure, non-linearity, has now disappeared due to an improvement in the design and due to a linearity test in Photonis prior to shipment. 

 

 

SDE Field Failures

 

The UB fuse failures (17 up to October 2004) were analysed by the CdF group and Mariela (see GAP Note GAP_2005_002). An important amount of the fuse failures is in relation with a regulator failure (7). For each of these cases, after the regulator has been changed, no other failure was detected.

 

The measurement of the general consumption of electronic in the field, gives a load generally close to 310 mA for 28 Volts voltage supply (batteries full), then for 18 Volts, the current value should not exceed 480 mA, which is under the fuse limit.

 

 

Figure 1. Current load and battery voltage on the tank Selknam (from GAP_2005_002).

 

 

It seems that there has been a bad batch of regulators which has caused part of the UB fuse failures.  For the moment, no action is taken to increase the fuse from 500 mV to 750 mV.

 

There are currently 17 E-kits back from the field waiting for further failure analysis in the SDE-Fabrica. The most of the E-kit failures are due to radios and UB fuses. A more complete report on the failures will be given in the March collaboration meeting.

 

Lightning hit

 

There is a clear hit of lightning on the PIQUILLIN. The cable cover of the antenna was burned, radio and Ekit needed to be replaced. Now PIQUILLIN is again taking data.

It seems that lightning hits are rather rare, this is a first clear case observed. Last year a big storm stopped 3-4 tanks but a simple reset on the UBs was enough to get them running again.

 

 

PMT field failures

 

Walter Fulgione, Javier and Fabian had a two weeks debug session, 6-19 December 2004 on the field failures. 44 field failures (tanks with failure) were studied, 17 PMTs, 5 E-kits, 6 SMA connectors and 1 radio were changed. 

 

Some of the PMT failures are due to instable behaviour. The figure below shows a muon peak as a function of time for PMT2 in tank MAITEN.  13 PMTs removed from the field were sent back to Photonis. Further tests for these PMTs will be performed in Torino.

 

The PMT field failures are carefully monitored. Some of the failures are due to connectors and can be repaired in the field. Some PMTs present very large variations as a function of temperature or are very unstable. For the moment, no particular cause has been found for the unstable temperature behaviour. Typically, these PMTs present no failures when they are re-tested in the PMT-House after their removal from the site. Furthermore, 2 such PMTs were tested in the temperature chamber of the IPNO without being able to reproduce the unstable behaviour. A more detailed report on the field failures will be given in the March collaboration meeting.

 

 

Figure 2. Unstable behaviour of muon peak (PMT2 MAITEN).

 

Solar panel cables (SD)

 

The solar panel cables currently deployed to the field have UV-resistance problems (see figure below).  A corrective action is currently planned by the SD group.

 

Cyclone testing

 

Ten front-end boards with the Cyclone chip have been fabricated in Wuppertal. All have passed the functionality and 5-days temperature tests in the temperature chamber with the 24h period of the temperature variation from –20C to +70C. FE boards were tested with internal pattern generator and all digital sections passed all tests successfully. Some problems were found in the analog sections.

Seven Cyclone front end boards were shipped to Malargue and Zbigniew and Xavier performed tests with the JAMIE test tank. A simple data acquisition program was used. Preliminary data collected from the tank for couple of days look very promising

The normal data acquisition requires the new version of the UB software. Laurent Guglielmi is currently working on it. The plan is to run data acquisition in a few tanks to check the full functionality and stability of the Cyclone design before the Critical Design Review.

 

LED assembly and tests

 

Ygor and Konstantin from MEPhI were in Malargue after the November collaboration meeting to set up a portable LED test facility, designed in MEPhI, for the LED flashers. This facility allows to study main parameters of the flashers by means of the reference PMT (which is the part of facility) and also to check how flasher drivers provide the linearity measurements. The PMT output pulses are analyzed by means of the two-channel digital oscilloscope (100 MSPS). We use signals from two different dynodes (from 8-th and from 11-th) to provide 105 dynamic range. Flexible software interface allows us to study different characteristics of both drivers and flasher as a whole. About 100 flashers were studied (after the flashers were potted). The flashers were observed to have large differences in the output luminosities.  Currently the flashers are used for tests and the variations in the light output are not crucial. However, care should be taken when flashers are used for linearity measurements.

 

 

SDE deployment and maintenance

 

There are currently about 687 tanks in the field, 652 of them have water and 602 are with electronics. The electronics deployment was stopped in December due to the lack of TPCBs. 100 TPCBs are currently in transit from US to Malargue and the deployment activities should start again next week. 

The deployment is proceeding smoothly with a rate of 10 E-kits per day.  Parallel to the deployment, Javier and Fabian also do maintenance. This week a fatal failure was discovered: batteries were stolen (see photo album).

 

 

WBS 3.0 Comms (Paul Clark – Leeds)

 

Progress Achieved in Communications Task during recent December Site Visit

 

Final Communications Tower at Loma Amarilla virtually completed.

 

All the surface detector wireless LAN antennas, cable and other equipment has been installed and the tower just requires installation of the microwave link to the Coihueco tower to be completed. This will happen before the next meeting.

 

 

Software progress – Commissioning

 

The comms system has suffered from an intermittent bug that has caused system availability to drop a few % below 100%. This was due to base-station radios 'disappearing from the network. This bug was found and solved during the December trip, we have not had a base-station disappear since we solved the problem in mid-December. According to site staff, all outages

experienced since mid-December have been due to power failures.

 

 

Software progress - performance monitoring

 

A brand new real-time comms system performance reporting system was written and installed during the last site visit. This system allows instant analysis of any radio link in the network by ARQ (packet error) rates, signal strength or network disconnections. This new facility allows the

operator to know that all is well and allows under-performing radio links to be quickly identified. Analysis may be done on individual links or whole sectors also enabling base-station performance to be analysed easily.

 

 

 

WBS 5.0 DPA/Offline- (Bruce Dawson, Markus Roth & Tom Paul)

 

Unfortunately Stefano Argiro departed Auger at the end of December; his DPA leadership responsibilities have since been reapportioned, with Bruce Dawson, Markus Roth and Tom Paul coordinating ongoing  efforts.  Bruce and Markus will act as the principle liaisons between

the offline software team the analysis tasks for FD and SD, respectively.  Their role will be to work together with analysis coordinators to ensure that the physics modules distributed with the

offline framework represent the best knowledge of the collaboration.  Tom will coordinate ongoing development of the framework machinery itself.

 

During the last collaboration meeting, a production readiness review was held.  The offline team is now working to address the concerns and suggestions of the committee.  The reorganization of the DPA leadership into three categories was in part meant to help address the committee's observation that the offline team and the analysis groups need to work in close concert from here on.

 

Since the collaboration meeting, Version 1.0.0 of the framework has been released, which includes improvements in many of the physics modules as well as the core framework code. 

 

A program to validate the SD simulation chain and begin a full production run has recently got underway, with Maximo Ave coordinating the efforts and with several contributors.  Comparisons of different hybrid geometry and FD profile reconstruction algorithms are also underway.

Significant progress has also been made getting the FD simulation chain to run reliably, and it will be crosschecked in detail against the old FDSim in the near future.  On the SD side, Darko Veberic and Markus have made considerable progress refining the reconstruction algorithms so

they are in good shape.  New interfaces to the CDAS calibration and event selection algorithms are also nearing completion. 

 

The offline databases for FD calibrations, SD monitoring, and some atmospheric monitoring are being filled and tested in preparation for wide scale distribution. 

 

The framework machinery has also been enhanced with new tools to make configuration simpler and to check configuration files for common errors. 

 

Near the end of January, a second DPA school was held in Salt Lake City, hosted by the University of Utah.  It was well attended and provided a useful forum not only to introduce the offline framework to new users, but to feed back ideas and concerns to framework developers. 

 

 

WBS 9.0 Observatory Operations – (Julio Rodriguez Martino – INFN)

 

The analysis of the FD data, from the point of view of the detector performance, was improved. The dead time corresponding to moonlight, bad weather or hardware/ software problems is now calculated using the DAQ log files and the information written to the e-log by the people in shift. The event rate is calculated for each run and several plots are generated, both in PostScript and ROOT format. The event rate and the total number of events are plotted, both for T2 and T3 triggers. This information is available from the FD web page: http://www.auger.org.ar/FD/
Several improvements are foreseen and a GAP note will soon be available containing
a detailed explanation of the analysis method. It is also proposed that this work is presented in the next ICRC.

Starting from January 2005, the data taking period is defined as all days when the moon fraction is 60 % or less. This means in practice that the period is 2 days longer than before.
It is still necessary to establish if those two extra days are worth from the point of view of the data quality.

We had some problems with the data taking. Some unstable behavior of the DAQ system, that will hopefully be solved soon, increased the dead time during the past months. More important during January were several thunderstorms that affected the normal operation. The lightning filter that used to be present in the T3 algorithm is not used anymore. It must be rewritten to
avoid the loss of important events due to its malfunction. Some hardware problems affected also the trigger rate. It is clear that these external factors should be handled by the trigger algorithm in a correct way, since they will sooner or later be present during the data taking period. The
responsible people have been contacted and the work is being organized to solve this problem as fast as possible.